§ 01

Permit authority

Code Enforcement Officer / Building Official

Street address
571 Lakeview Drive, China, ME 04358
Coverage
Town of China; all construction and land use within town limits
§ 02

When a permit is required

Permit triggers and exempt work for China

Permits must be obtained BEFORE starting any project or fines and possible removal may result; new construction, additions, renovations, demolitions, driveways, signs, plumbing, and shoreland zone work

Not explicitly listed; contact CEO
Deck standards and fastening guides available on website; contact CEO to confirm if permit needed
  • Exempt Not explicitly listed; contact CEO
  • Exempt Deck standards and fastening guides available on website; contact CEO to confirm if permit needed

Note: Exempt from building permit does not mean exempt from zoning and planning requirements. Confirm edge cases with the permitting office before proceeding.

Required documents
  • Building Permit Application or CEO Permit Application
  • site plan
  • plumbing application (internal)
  • variance and appeal application if needed
  • DEP shoreland zone certifications for applicable projects
Building code
References IRC (International Residential Code) including frost-protected shallow foundations and egress window standards; MUBEC adoption status -- contact CEO (China population under 4,000)
Contractor requirements
Contractors in shoreland zone must be DEP-certified in erosion and sedimentation control; electrical and plumbing require state licensing

Source: Code Enforcement Officer / Building Official ↗

§ 03

Application process

Typical processing: CEO has 35 days to issue permit once complete application received

  1. 01
    Contact CEO Nicholas French at ceo@chinamaine.org or (207) 445-2014 option 5
  2. 02
    Download building permit application or CEO permit application from chinamaine.org
  3. 03
    Complete application; attach site plan and required supporting documents
  4. 04
    Submit to town office at 571 Lakeview Drive
  5. 05
    CEO has 35 days to issue or deny permit after complete application received
  6. 06
    Fee collected per fee schedule (updated 2/24/2025)
  7. 07
    Permit issued; keep on site; obtain required inspections
  8. 08
    For shoreland zone work: all contractors must be DEP-certified in erosion and sediment control

Typical processing time: CEO has 35 days to issue permit once complete application received

Source: Code Enforcement Officer / Building Official ↗

§ 04

Fee schedule

China building permit fees

Fee type
Amount
01
Plan check fee
Included in review fees per fee schedule

Contact office

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • ceo@chinamaine.org (email)
  • (207) 445-2014 (phone)
Inspection hours
Monday, Tuesday, Thursday, Friday 7:30 AM-4:30 PM; closed Wednesday; first and last Saturday 8:00 AM-11:00 AM

Source: Code Enforcement Officer / Building Official ↗

§ 06

Frequently asked

Common questions about China permits

01 Do I need a building permit in China, ME?
Permits must be obtained BEFORE starting any project or fines and possible removal may result; new construction, additions, renovations, demolitions, driveways, signs, plumbing, and shoreland zone work
02 How do I apply for a building permit in China, ME?
To apply for a building permit in China, ME, follow these steps: 1. Contact CEO Nicholas French at ceo@chinamaine.org or (207) 445-2014 option 5 2. Download building permit application or CEO permit application from chinamaine.org 3. Complete application; attach site plan and required supporting documents 4. Submit to town office at 571 Lakeview Drive 5. CEO has 35 days to issue or deny permit after complete application received 6. Fee collected per fee schedule (updated 2/24/2025) 7. Permit issued; keep on site; obtain required inspections 8. For shoreland zone work: all contractors must be DEP-certified in erosion and sediment control
03 How long does it take to get a building permit in China, ME?
Building permit processing times in China, ME typically run CEO has 35 days to issue permit once complete application received. Timelines can vary based on project complexity and current department workload.
04 What work is exempt from building permits in China, ME?
Not all construction work requires a permit in China, ME. The following work is generally exempt: Not explicitly listed; contact CEO; Deck standards and fastening guides available on website; contact CEO to confirm if permit needed. Note: Exempt from building permit does not mean exempt from zoning and planning requirements. Confirm edge cases with the permitting office before proceeding. When in doubt, confirm with the local building department before starting work.
05 How do I schedule a building inspection in China, ME?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in China, ME via: ceo@chinamaine.org, (207) 445-2014.
last verified April 2026 source Code Enforcement Officer / Building Official ↗ entry id permits/maine/kennebec/china