On this page 6
When a permit is required
Permit triggers and exempt work for Cave City
Any new structure, addition, alteration, or demolition within the city; the ordinance prohibits starting work until a permit is issued.
- Exempt Agricultural-only buildings on ten or more acres
Note: The Kentucky Residential Code exemptions apply; the county office highlights agricultural-only buildings on ten or more acres as exempt, while the rest of the code governs other exemptions.
- Application with owner and contractor information
- Project description and property address
- Code classifications
- Sufficient plans complying with the Kentucky Uniform State Building Code and local zoning
- Building code
- Kentucky Uniform State Building Code plus the Kentucky Residential/Building Code and International Property Maintenance Code (per the county building inspector).
- Permit validity
- Permits follow the standard 180-day validity unless extended.
- Owner-builder
- Owner-occupants can perform property electrical work; landlords, rental properties, or work for others must hire a licensed electrician.
- Contractor requirements
- Electrical contractors must hold the appropriate Kentucky license; other trades comply with statewide licensing enforced through plan review.
Source: Cave City Building Inspector ↗
Application process
Typical processing: Joint City-County Planning Commission zoning compliance certificates have a ten working day deadline; permit review timelines are managed by the inspector.
- 01 Do not begin construction or alterations until the Cave City Building Inspector issues a permit (Section 150.18(A)).
- 02 Submit a complete application listing the property, contractor, description, construction classification, estimated cost, and compliance with the Kentucky Uniform State Building Code along with the required plans (Section 150.18(B)).
- 03 Pay the building permit fee, which covers plan review and inspections, and allow the City of Glasgow Building Inspector to review for Kentucky code and local compliance.
- 04 Coordinate with the Joint City-County Planning Commission for zoning compliance certificates, which are due within ten working days for municipalities under that commission.
- 05 Schedule inspections through (270) 651-3921 once the permit is issued and do not occupy the structure before the final inspection and Certificate of Occupancy.
Typical processing time: Joint City-County Planning Commission zoning compliance certificates have a ten working day deadline; permit review timelines are managed by the inspector.
Source: Cave City Building Inspector ↗
Fee schedule
Cave City building permit fees
Fees are collected with the permit application, either online through Cloudpermit or at the inspector's office at 200 South Green St.
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- (270) 651-3921 (phone)
- Scheduling deadline
- Calls before 9:00 AM CST are usually handled the same day.
- Inspection hours
- Five days a week
- Time windows
- Same-day inspections available for calls before 9:00 AM CST; later requests are handled as staffing allows.
Typical sequence: Kentucky Residential/Building Code checkpoints, including footing, foundation, framing, rough mechanical/electrical/plumbing, and final, as detailed in the checklists.
Source: Cave City Building Inspector ↗
Frequently asked
Common questions about Cave City permits
01 Do I need a building permit in Cave City, KY? ▸
02 How much does a building permit cost in Cave City, KY? ▸
03 How do I apply for a building permit in Cave City, KY? ▸
04 How long does it take to get a building permit in Cave City, KY? ▸
05 What work is exempt from building permits in Cave City, KY? ▸
06 How do I schedule a building inspection in Cave City, KY? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Cave City Building Inspector before applying. Jaspector is not legal advice.