jaspector
City building permits

City of Beloit

How to apply for a building permit in City of Beloit, Kansas. Permit authority, application steps, fees, and inspection requirements.

Min. permit fee
$25.00
Last verified
April 2026
On this page 5
§ 01

Permit authority

City of Beloit, Building and Zoning / Building Inspector functions.

Street address
119 North Hersey Avenue, P.O. Box 567, Beloit, Kansas 67420
Coverage
City limits of Beloit.
§ 02

When a permit is required

Permit triggers and exempt work for Beloit

Prior to construction, enlargement, alteration, repair, movement, demolition, or change of occupancy of any building or structure.

Steps from start to issued permit:
When permit required: Prior to construction, enlargement, alteration, repair, movement, demolition, or change of occupancy of any building or structure.
Formula: 0.25 percent of estimated project cost, with a $25.00 minimum
No public exemption list was found in the sources reviewed.
City forms source: [Residential Zoning and Building Permit form](https://beloitks.org/api/blob/viewBlob?i=M3R818EG%2FRXuH22nniFkRpaktrZd%252BcSq8tL8Xt%252BMg8oBGY%252Bu3IVqevo1xwHV8F2V&rf=t)
Building inspector contact is embedded in the form.
  • Exempt Steps from start to issued permit:
  • Exempt When permit required: Prior to construction, enlargement, alteration, repair, movement, demolition, or change of occupancy of any building or structure.
  • Exempt Formula: 0.25 percent of estimated project cost, with a $25.00 minimum
  • Exempt No public exemption list was found in the sources reviewed.
  • Exempt City forms source: [Residential Zoning and Building Permit form](https://beloitks.org/api/blob/viewBlob?i=M3R818EG%2FRXuH22nniFkRpaktrZd%252BcSq8tL8Xt%252BMg8oBGY%252Bu3IVqevo1xwHV8F2V&rf=t)
  • Exempt Building inspector contact is embedded in the form.
Required documents
  • Site plan, construction drawings and plans, project description, contractor identification if known, cost estimate.
Building code
The published form references the Uniform Building Code, Section 108.2.
Permit validity
Permits expire after 6 months if construction has not begun or the project languishes for 6 months or longer.
Owner-builder
Application forms are completed by the property owner or designated agent/contractor.
Contractor requirements
Contractor information is requested; the form lists separate trades if known.
§ 03

Fee schedule

Beloit building permit fees

Fee type
Amount
01
Minimum permit fee
$25.00
02
Plan check fee
Not separately published on the form reviewed.
03
Permit fee formula
0.25 percent of estimated project cost, with a $25.00 minimum
04
Reinspection fee
Not separately published on the form reviewed.
§ 04

Required inspections

Scheduling and sequence

How to schedule
  • Call 785-738-3553 or 785-7419 for inspection before concealing work or moving to the next stage. (phone)
Inspection hours
Daytime hours for site access are referenced for the Building and Zoning Official.

Typical sequence: Site/zoning, plumbing ground run, sewer service, water service, fence, footing, foundation, floor, wall construction, roof/ceiling, electrical, mechanical, plumbing, final, building safety.

§ 05

Frequently asked

Common questions about Beloit permits

01 Do I need a building permit in Beloit, KS?
Prior to construction, enlargement, alteration, repair, movement, demolition, or change of occupancy of any building or structure.
02 How much does a building permit cost in Beloit, KS?
Building permit fees in Beloit, KS are set by the local building department and vary by project type and valuation. The minimum permit fee is $25.00. Fees are calculated as: 0.25 percent of estimated project cost, with a $25.00 minimum. Plan check fee: Not separately published on the form reviewed..
03 How long does it take to get a building permit in Beloit, KS?
Building permit processing times in Beloit, KS typically run Not published in the form. The city form states no permit will be issued without required drawings and plans.. Timelines can vary based on project complexity and current department workload.
04 What work is exempt from building permits in Beloit, KS?
Not all construction work requires a permit in Beloit, KS. The following work is generally exempt: Steps from start to issued permit:; When permit required: Prior to construction, enlargement, alteration, repair, movement, demolition, or change of occupancy of any building or structure.; Formula: 0.25 percent of estimated project cost, with a $25.00 minimum; No public exemption list was found in the sources reviewed.; City forms source: [Residential Zoning and Building Permit form](https://beloitks.org/api/blob/viewBlob?i=M3R818EG%2FRXuH22nniFkRpaktrZd%252BcSq8tL8Xt%252BMg8oBGY%252Bu3IVqevo1xwHV8F2V&rf=t); Building inspector contact is embedded in the form.. When in doubt, confirm with the local building department before starting work.
05 How do I schedule a building inspection in Beloit, KS?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Beloit, KS via: Call 785-738-3553 or 785-7419 for inspection before concealing work or moving to the next stage..
last verified April 2026 entry id permits/kansas/mitchell/beloit

Educational reference. Permit rules and fees change — confirm current requirements directly with City of Beloit, Building and Zoning / Building Inspector functions. before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Mitchell County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Mitchell County jurisdictions →