City building permits

City of Roland

How to apply for a building permit in City of Roland, Iowa. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

City of Roland

Street address
120 N Main St., PO Box 228, Roland, IA 50236
Coverage
Covers the incorporated City of Roland.
Additional resources
§ 02

When a permit is required

Permit triggers and exempt work for Roland

Roland publishes building and trade permit materials. A search-engine snippet from the city's fence permit page states a building permit can be obtained from the city before fence installation.

Trade permits are not required for new residential construction per the reviewed trade permit form.
  • Exempt Trade permits are not required for new residential construction per the reviewed trade permit form.

Note: No broader public exemption list was identified.

Required documents
  • Completed permit form
  • Building plans
Building code
Not publicly summarized on the reviewed Roland materials.
Permit validity
Trade permits expire after 12 months or if work is abandoned for 120 days or fails to begin within 180 days.
Owner-builder
Not publicly summarized in a separate Roland guidance sheet reviewed here.
Contractor requirements
Trade permit requests contractor state license number. Trade permits are not required for new residential construction per the reviewed trade permit form.

Source: City of Roland ↗

§ 03

Application process

Typical processing: Not publicly posted on the reviewed Roland materials.

  1. 01
    Obtain the applicable building or trade permit form from the City of Roland.
  2. 02
    Complete the permit form and submit any building plans with the application.
  3. 03
    Send completed materials to cityofroland@gmail.com or coordinate with City Hall.
  4. 04
    Wait for city approval before starting work.
  5. 05
    Schedule required inspections with Veenstra and Kimm.

Typical processing time: Not publicly posted on the reviewed Roland materials.

Source: City of Roland ↗

§ 04

Fee schedule

Effective September 2023

Fee type
Amount
01
Minimum permit fee
Residential trade alteration and appliance replacement permits are $75.00 each. Residential solar base permit is $125.00.
02
Plan check fee
Not separately listed on the reviewed Roland trade permit form
03
Permit fee formula
Commercial trade permit fee is $50 for the first $1,000 of valuation, then $5 for each additional $1,000
04
Trade permit fee
$75-$125 depending on trade and type

Trade permit form shows total fee is calculated on the form and paid through the city process

Fees change periodically. Confirm at the official fee schedule ↗ (effective September 2023) before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • Call Veenstra and Kimm at 515-850-2980 (phone)
  • buildinginspection@v-k.net (email)
Scheduling deadline
24-hour notice required

Typical sequence: Depends on project type; city uses Veenstra and Kimm for required inspections

Source: City of Roland ↗

§ 06

Frequently asked

Common questions about Roland permits

01 Do I need a building permit in Roland, IA?
Roland publishes building and trade permit materials. A search-engine snippet from the city's fence permit page states a building permit can be obtained from the city before fence installation.
02 How much does a building permit cost in Roland, IA?
Building permit fees in Roland, IA are set by the local building department and vary by project type and valuation. The minimum permit fee is Residential trade alteration and appliance replacement permits are $75.00 each. Residential solar base permit is $125.00.. Fees are calculated as: Commercial trade permit fee is $50 for the first $1,000 of valuation, then $5 for each additional $1,000. Plan check fee: Not separately listed on the reviewed Roland trade permit form.
03 How do I apply for a building permit in Roland, IA?
To apply for a building permit in Roland, IA, follow these steps: 1. Obtain the applicable building or trade permit form from the City of Roland. 2. Complete the permit form and submit any building plans with the application. 3. Send completed materials to cityofroland@gmail.com or coordinate with City Hall. 4. Wait for city approval before starting work. 5. Schedule required inspections with Veenstra and Kimm.
04 How long does it take to get a building permit in Roland, IA?
Building permit processing times in Roland, IA typically run Not publicly posted on the reviewed Roland materials.. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Roland, IA?
Not all construction work requires a permit in Roland, IA. The following work is generally exempt: Trade permits are not required for new residential construction per the reviewed trade permit form.. Note: No broader public exemption list was identified. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Roland, IA?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Roland, IA via: Call Veenstra and Kimm at 515-850-2980, buildinginspection@v-k.net. 24-hour notice required.
last verified April 2026 source City of Roland ↗ entry id permits/iowa/story/roland-city

Educational reference. Permit rules and fees change — confirm current requirements directly with City of Roland before applying. Jaspector is not legal advice.