§ 01

Permit authority

City of Virden Building Department

Street address
101 W. Jackson St., Virden, IL 62690
Coverage
Within city limits.
Online portal
City of Virden
In-person
§ 02

When a permit is required

Permit triggers and exempt work for Virden

New homes, manufactured homes, additions, accessory buildings.

Standard cosmetic repairs
Landscaping
  • Exempt Standard cosmetic repairs
  • Exempt Landscaping
Required documents
  • Site plan
  • 911 address
  • Construction specs
Building code
2021 IBC/IRC.
Permit validity
1 year.
Owner-builder
Owner-builders are allowed.
Contractor requirements
Must provide insurance certificate.
§ 03

Application process

Typical processing: 5-7 business days

  1. 01
    Submit form with site plan and valuation.
  2. 02
    Review and approval by Building Inspector.

Typical processing time: 5-7 business days

Source: City of Virden Building Department ↗

§ 04

Fee schedule

Virden building permit fees

Fee type
Amount
01
Minimum permit fee
$50.00
02
Permit fee formula
Flat fees for many residential items; valuation for commercial
03
Penalty (no permit)
$100 penalty for no permit

Cash or check at Water Office/City Hall.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • (217) 965-5805 (phone)
Inspection hours
Morning appointments preferred

Typical sequence: Typical sequence: Foundation, Rough, Final.

§ 06

Frequently asked

Common questions about Virden permits

01 Do I need a building permit in Virden, IL? ▸
New homes, manufactured homes, additions, accessory buildings.
02 How much does a building permit cost in Virden, IL? ▸
Building permit fees in Virden, IL are set by the local building department and vary by project type and valuation. The minimum permit fee is $50.00. Fees are calculated as: Flat fees for many residential items; valuation for commercial.
03 How do I apply for a building permit in Virden, IL? ▸
To apply for a building permit in Virden, IL, follow these steps: 1. Submit form with site plan and valuation. 2. Review and approval by Building Inspector.
04 How long does it take to get a building permit in Virden, IL? ▸
Building permit processing times in Virden, IL typically run 5-7 business days. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Virden, IL? ▸
Not all construction work requires a permit in Virden, IL. The following work is generally exempt: Standard cosmetic repairs; Landscaping. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Virden, IL? ▸
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Virden, IL via: (217) 965-5805.