Code adoption
2018 ICC Series (moving to 2021/2025)
Avg processing
1-2 weeks (review is external)
Min. permit fee
$35
Last verified
April 2026
On this page 6
§ 01

Permit authority

Building Department (Contracted)

Street address
308 E. Comanche Ave, Shabbona, IL 60550
Coverage
Village limits.
§ 02

When a permit is required

Permit triggers and exempt work for Shabbona

New homes, additions, structural alterations, decks, detached garages, in-ground pools.

Sheds <200 sq. ft.
Roof repairs/replacements
Retaining walls <4 feet
Finish work (painting, flooring)
Decks <200 sq. ft. and <30" above grade (detached)
Windows/Doors (replacement same size)
Siding
  • Exempt Sheds <200 sq. ft.
  • Exempt Roof repairs/replacements
  • Exempt Retaining walls <4 feet
  • Exempt Finish work (painting, flooring)
  • Exempt Decks <200 sq. ft. and <30" above grade (detached)
  • Exempt Windows/Doors (replacement same size)
  • Exempt Siding
Required documents
  • Application
  • Plat of Survey
  • 2 sets of plans
Building code
2018 ICC Series (moving to 2021/2025)
Permit validity
6 months to start
Owner-builder
Residential owners may perform work.
Contractor requirements
Registration voluntary but recommended.
§ 03

Application process

Typical processing: 1-2 weeks (review is external)

  1. 01
    Complete permit application from Village website.
  2. 02
    Submit to Village Hall with Plat of Survey and plans.
  3. 03
    Plans sent to B&F Construction Code Services for review.
  4. 04
    Village notifies applicant of approval/fees.
  5. 05
    Pay fee at Village Hall and receive permit.

Typical processing time: 1-2 weeks (review is external)

Source: Building Department (Contracted) ↗

§ 04

Fee schedule

Shabbona building permit fees

Fee type
Amount
01
Minimum permit fee
$35
02
Plan check fee
Included in total package
03
Permit fee formula
Mixed flat fees and inspection costs
04
Reinspection fee
$55+

Check or cash

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • 847-428-7010 (phone)
Inspection hours
Scheduled through B&F

Typical sequence: Standard ICC sequence

§ 06

Frequently asked

Common questions about Shabbona permits

01 Do I need a building permit in Shabbona, IL? ▸
New homes, additions, structural alterations, decks, detached garages, in-ground pools.
02 How much does a building permit cost in Shabbona, IL? ▸
Building permit fees in Shabbona, IL are set by the local building department and vary by project type and valuation. The minimum permit fee is $35. Fees are calculated as: Mixed flat fees and inspection costs. Plan check fee: Included in total package.
03 How do I apply for a building permit in Shabbona, IL? ▸
To apply for a building permit in Shabbona, IL, follow these steps: 1. Complete permit application from Village website. 2. Submit to Village Hall with Plat of Survey and plans. 3. Plans sent to B&F Construction Code Services for review. 4. Village notifies applicant of approval/fees. 5. Pay fee at Village Hall and receive permit.
04 How long does it take to get a building permit in Shabbona, IL? ▸
Building permit processing times in Shabbona, IL typically run 1-2 weeks (review is external). Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Shabbona, IL? ▸
Not all construction work requires a permit in Shabbona, IL. The following work is generally exempt: Sheds <200 sq. ft.; Roof repairs/replacements; Retaining walls <4 feet; Finish work (painting, flooring); Decks <200 sq. ft. and <30" above grade (detached); Windows/Doors (replacement same size); Siding. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Shabbona, IL? ▸
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Shabbona, IL via: 847-428-7010.
last verified April 2026 source Building Department (Contracted) ↗ entry id permits/illinois/dekalb/shabbona

Educational reference. Permit rules and fees change — confirm current requirements directly with Building Department (Contracted) before applying. Jaspector is not legal advice.