When a permit is required
Permit triggers and exempt work for DeKalb County
New construction, additions, alterations, decks, sheds, fences, solar panels, and major repairs.
- Exempt One-story detached accessory structures 120 sq. ft. or less (still must meet setbacks)
- Exempt Fences 3 feet or less in height (front yard)
- Exempt Painting, papering, tiling, carpeting, cabinets, countertops, and similar finish work
- Exempt Swings and other playground equipment
- Exempt Window awnings supported by an exterior wall
- Permit Application
- Plat of Survey
- Building Plans
- Health Department approval (if applicable)
- Notarized Letters of Intent from licensed trades
- Building code
- 2021 IRC, 2021 IBC, 2023 NEC (State mandate), 2014 Illinois Plumbing Code
- Permit validity
- Construction must start within 180 days; valid for 12 months. Void if no inspections for 180 days.
- Owner-builder
- Owners may perform work on their own primary residence; still requires permits and inspections.
- Contractor requirements
- Plumbers and Roofers must provide state license numbers. Electricians must be licensed by a municipality that tests.
Application process
Typical processing: 1 to 3 weeks
- 01 Determine if a permit is required for the specific project.
- 02 Complete the Permit Application form (available on website).
- 03 Submit two sets of building plans and a Plat of Survey showing proposed improvements.
- 04 For projects with well/septic, obtain Health Department approval first (815-758-6673).
- 05 Submit Notarized Letters of Intent from licensed trades (Plumbing, Electrical, Roofing, HVAC).
- 06 Pay application fee.
- 07 Undergo Zoning Review and Site Inspection (stakes must be in place).
- 08 Permit issuance following plan approval (typically 1-3 weeks).
Typical processing time: 1 to 3 weeks
Fee schedule
DeKalb County building permit fees
Checks or credit cards (with service fee) accepted
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- 815-895-7188 (phone)
- Scheduling deadline
- Call at least 24 hours in advance
- Inspection hours
- Monday - Friday, business hours
Typical sequence: Footing, Foundation/Walls, Framing/Rough-in (Elec/Plumb/HVAC), Insulation, Final
Frequently asked
Common questions about unincorporated DeKalb County permits
01 Do I need a building permit in unincorporated DeKalb County, IL? ▸
02 How much does a building permit cost in unincorporated DeKalb County, IL? ▸
03 How do I apply for a building permit in unincorporated DeKalb County, IL? ▸
04 How long does it take to get a building permit in unincorporated DeKalb County, IL? ▸
05 What work is exempt from building permits in unincorporated DeKalb County, IL? ▸
06 How do I schedule a building inspection in unincorporated DeKalb County, IL? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with DeKalb County Community Development Department before applying. Jaspector is not legal advice.