Village of Caledonia, IL - 2026 Building Permit Guide
How to apply for a building permit in Village of Caledonia, Illinois. Permit authority, application steps, fees, and inspection requirements.
Permit Authority
Serves properties within the incorporated limits of the Village of Caledonia. Properties in Caledonia Township but outside the village limits fall under unincorporated Boone County jurisdiction.
- Department
- Village of Caledonia
- Address
- P.O. Box 34, Caledonia, Illinois 61011
- Phone
- (815) 955-3001
- ClerkVofC61011@gmail.com
- Website
- https://villageofcaledonia.com/
Application Process
- For village-issued permits (fences, chicken coops, window replacements): submit a permit application to the Village Clerk including intent statement, plans, contractor information with proof of insurance, and project timeline.
- Pay applicable fees.
- Permit is valid for 1 year from issuance.
- Inspections must be arranged and conducted before, during, and after project completion. Inspection timing is determined before the permit is issued.
- NOTE: If work begins without a permit, B&F Construction Code Services will issue a Stop Work Order.
Source: Village of Caledonia
General Requirements
State-required licensed permits (via B&F): roofing, decks, porches, new construction, additions, sheds, plumbing, electrical, pools with electrical components, detached garages, solar panels. Village-issued permits: fences, chicken coops, window replacements.
Required Documents
- Statement of intent
- Plans/drawings
- Contractor name and proof of insurance
- Project timeline
- Permit validity
- Permits are valid for 1 year from date of issuance.
- Building code
- Under Public Act 103-0510 (effective January 1, 2025), Caledonia must enforce codes at least as stringent as the 2021 IBC, 2021 IRC, 2021 IEBC, NEC 2023, Illinois Energy Conservation Code, Illinois Accessibility Code, and Illinois Plumbing Code. Confirm actual adopted ordinances with the Village Clerk or by downloading the Municipal Code PDF at https://villageofcaledonia.com/ordinances. NOTE: Some codes may have been revised since the original print and may not be current on the website.
- Contractor requirements
- Contractor must provide proof of insurance. IDFPR licenses required for electricians and plumbers. No statewide general contractor license. Confirm any local requirements with the clerk.
Fees
- Plan check fee
- B&F Construction Code Services fees apply for plan review; contact (847) 428-7010 or planreview@bfccs.org
Work That Does NOT Require a Permit
Contact the Village of Caledonia to confirm whether your project requires a permit before starting work.
Inspections
How to Schedule
- (847) 428-7010 (phone)
Typical inspection sequence: Inspections required before, during, and after project completion. Specific timing is determined with the applicant before the permit is issued.
Additional Resources
- Building code: Under Public Act 103-0510 (effective January 1, 2025), Caledonia must enforce codes at least as stringent as the 2021 IBC, 2021 IRC, 2021 IEBC, NEC 2023, Illinois Energy Conservation Code, Illinois Accessibility Code, and Illinois Plumbing Code. Confirm actual adopted ordinances with the Village Clerk or by downloading the Municipal Code PDF at https://villageofcaledonia.com/ordinances. NOTE: Some codes may have been revised since the original print and may not be current on the website.
- Verify contractor license: IDFPR License Lookup
- Zoning information: View zoning info
- Village building permits page
- Village ordinances
- B&F Construction Code Services
- License lookup guide: Illinois Contractor License Requirements
- Contract template: Illinois Homeowner-Contractor Agreement
- Illinois hub: Illinois Contractor License & Permit Hub
Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Village of Caledonia before applying.
Frequently Asked Questions
Village of Caledonia Building Permit FAQ
- Do I need a building permit in Village of Caledonia, IL?
- State-required licensed permits (via B&F): roofing, decks, porches, new construction, additions, sheds, plumbing, electrical, pools with electrical components, detached garages, solar panels. Village-issued permits: fences, chicken coops, window replacements.
- How do I apply for a building permit in Village of Caledonia, IL?
- 1. For village-issued permits (fences, chicken coops, window replacements): submit a permit application to the Village Clerk including intent statement, plans, contractor information with proof of insurance, and project timeline. 2. Pay applicable fees. 3. Permit is valid for 1 year from issuance. 4. Inspections must be arranged and conducted before, during, and after project completion. Inspection timing is determined before the permit is issued. 5. NOTE: If work begins without a permit, B&F Construction Code Services will issue a Stop Work Order.
- How do I schedule a building inspection in Village of Caledonia, IL?
- Inspections can be scheduled via: (847) 428-7010.
Need help with your project?
Navigating permits in Village of Caledonia can be complicated.
Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.
Learn how Jaspector worksOther cities in Boone County
View all Boone County jurisdictions →