When a permit is required
Permit triggers and exempt work for McCall
It is unlawful to perform any construction, improvement, extension, alteration, or demolition without first procuring a permit. Specific triggers: Building permits for all construction and structural changes; roof permits for all re-roofing; deck permits for decks over 200 sq ft or over 30 inches off ground; attached structures require permits regardless of size.
Note: Contact City of McCall Building Department for exemption details.
- Building permit application
- Plans stamped by licensed architect or engineer with certification of 2018 International Code compliance
- Project description and scope
- Site plan
- Building code
- 2018 International Building Code (IBC), 2018 International Energy Conservation Code (IECC)
- Contractor requirements
- Contractors must hold a valid McCall Business License. Sales or use tax required on all building materials.
Application process
Typical processing: Approximately 2–8 weeks, depending on seasonal demand (May–October typically very busy).
- 01 Contact the City of McCall Building Department to coordinate submission and make an appointment.
- 02 Prepare plans stamped by a licensed architect or engineer certified to comply with 2018 International Codes and City of McCall Ordinances.
- 03 Submit application and plans to the Building Department.
- 04 City staff reviews application for completeness and code compliance.
- 05 Pay applicable permit, plan review, and impact fees.
- 06 Respond to any plan review comments or correction requests if required.
- 07 Obtain permit before starting construction.
- 08 Schedule required inspections throughout construction.
Typical processing time: Approximately 2–8 weeks, depending on seasonal demand (May–October typically very busy).
Required inspections
Scheduling and sequence
- 208-634-7052 (phone)
- Scheduling deadline
- 24-hour notice required for inspection requests.
- Inspection hours
- Monday–Thursday, 7:30 a.m.–5:30 p.m.
Frequently asked
Common questions about McCall permits
01 Do I need a building permit in McCall, ID? ▸
02 How do I apply for a building permit in McCall, ID? ▸
03 How long does it take to get a building permit in McCall, ID? ▸
04 How do I schedule a building inspection in McCall, ID? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with City of McCall Building Department before applying. Jaspector is not legal advice.