When a permit is required
Permit triggers and exempt work for Donnelly
A building permit is required to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure.
Note: Contact City of Donnelly for exemption details.
- Building permit application
- Two sets of plans (18" × 24" or 24" × 36") stamped by licensed architect or engineer
- Two sets of structural calculations (8.5" × 11") stamped by licensed engineer
- Two sets of to-scale site plans showing dwelling site, well site, septic site, and replacement septic site
- Building code
- 2018 International Building Code (IBC), 2018 International Energy Conservation Code (IECC)
- Contractor requirements
- Contractors engaged in projects valued at $2,000 or more must be registered with the State of Idaho.
Source: City of Donnelly ↗
Application process
Typical processing: Approximately 2–8 weeks, depending on workload. May–October typically very busy.
- 01 Contact City of Donnelly to coordinate submission and permit requirements.
- 02 Prepare two sets of plans (18" × 24" or 24" × 36") stamped by a licensed architect or engineer certified to comply with 2018 International Codes and City of Donnelly Ordinances.
- 03 Prepare two sets of structural calculations on 8.5" × 11" paper stamped by a licensed engineer.
- 04 Prepare two sets of to-scale site plans showing dwelling site, well site, septic site, and replacement septic site.
- 05 Submit application, plans, and site plans to City of Donnelly.
- 06 City staff reviews for code compliance.
- 07 Pay applicable permit and plan review fees, plus impact fees.
- 08 Obtain permit and proceed with construction.
- 09 Submit electrical, plumbing, and HVAC permits to State of Idaho (DOPL) separately.
Typical processing time: Approximately 2–8 weeks, depending on workload. May–October typically very busy.
Source: City of Donnelly ↗
Required inspections
Scheduling and sequence
- Contact City of Donnelly (phone)
- Scheduling deadline
- 24-hour notice required for all inspection requests.
Typical sequence: Valley County currently performs all inspections for the City of Donnelly.
Source: City of Donnelly ↗
Frequently asked
Common questions about Donnelly permits
01 Do I need a building permit in Donnelly, ID? ▸
02 How do I apply for a building permit in Donnelly, ID? ▸
03 How long does it take to get a building permit in Donnelly, ID? ▸
04 How do I schedule a building inspection in Donnelly, ID? ▸