How to apply for a building permit in unincorporated Upson County, Georgia. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 5
§ 01

Permit authority

Upson County Building and Zoning Department

Street address
305 S Hightower Street, Suite D100, Thomaston, GA 30286
Coverage
The county Building and Zoning Department handles permitting for unincorporated Upson County. The county and City of Thomaston have separate building inspection programs. The Upson County zoning ordinance applies to unincorporated Upson County.
Additional resources
§ 02

When a permit is required

Permit triggers and exempt work for Upson County

The county's public permitting page and published application materials show permits are required for new home builds and other construction handled through the Building and Zoning office. The county also publishes separate applications or packets for demolition, manufactured homes, swimming pools, and land disturbance. No single county public handout was found that lists every permit trigger and every exemption.

Required documents
  • Completed permit application and landowner affidavit
  • Hard-copy plans
  • Site plan
  • Project valuation
  • Contractor and subcontractor information
  • Map and parcel information
  • Power provider
  • Zoning and floodplain information
  • Where applicable: COMcheck, erosion permit, driveway certificate of compliance, septic permit, well permit, homeowner inspection checklist, and homeowner affidavit
Building code
Georgia state minimum standard construction codes apply statewide. Upson County's zoning ordinance also references 'Upson County Building Codes (as amended)' as adopted by reference. No separate public county webpage listing local construction-code amendments was found.
Owner-builder
The county's new-construction requirements state state-licensed contractors are required to pull permits unless the owner pulls the permit for an owner-occupied home. The county also publishes a Residential by Owner homeowner affidavit and homeowner inspection procedures checklist.
Contractor requirements
The county's published requirements state contractors and subcontractors must submit copies of their state licenses and occupational tax certificates, must sign the permit before their trade work starts, and must do so before a certificate of occupancy will be issued. Georgia residential contractor licensing rules also apply statewide.
§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Review the county Building and Zoning page and determine whether related approvals are also needed. The county states land clearing of one acre or more requires a land disturbance permit first.
  2. 02
    Download and complete the county Building Permit Application and Land Owner Permit Affidavit from the county page.
  3. 03
    Email, fax, or mail the application package to the county. The county expressly directs that all permit applications be emailed to garagon@upsoncountyga.org.
  4. 04
    Deliver hard-copy construction plans to the Building and Zoning office. The county states plans must be hard copies, 36x24 or larger, and will not accept construction plans by email.
  5. 05
    Submit the required supporting materials. The county's published new-construction requirements call for project value, contractor and subcontractor information, power provider, map and parcel data, acreage, physical address, site plan, zoning and floodplain information, two sets of plans, and as applicable COMcheck, erosion permit, driveway certificate of compliance, septic permit, well permit, homeowner checklist, and homeowner affidavit.
  6. 06
    Wait for county review and permit processing. The county page states staff will get in touch after the permit has been processed.
  7. 07
    Schedule and complete required inspections through the county program before final approval and occupancy.

Source: Upson County Building and Zoning Department ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • 706-647-1297 (phone)
Inspection hours
Monday through Friday, 8:00 a.m. to 5:00 p.m.; closed every Tuesday from 8:30 a.m. to 9:30 a.m. for a staff meeting.
Time windows
Monday through Friday, 8:00 a.m. to 5:00 p.m.; closed every Tuesday from 8:30 a.m. to 9:30 a.m. for a staff meeting.

Typical sequence: The county page states Upson County requires inspections for footings, framing, plumbing, electrical, HVAC, and final inspection.

§ 05

Frequently asked

Common questions about unincorporated Upson County permits

01 Do I need a building permit in unincorporated Upson County, GA?
The county's public permitting page and published application materials show permits are required for new home builds and other construction handled through the Building and Zoning office. The county also publishes separate applications or packets for demolition, manufactured homes, swimming pools, and land disturbance. No single county public handout was found that lists every permit trigger and every exemption.
02 How do I apply for a building permit in unincorporated Upson County, GA?
To apply for a building permit in unincorporated Upson County, GA, follow these steps: 1. Review the county Building and Zoning page and determine whether related approvals are also needed. The county states land clearing of one acre or more requires a land disturbance permit first. 2. Download and complete the county Building Permit Application and Land Owner Permit Affidavit from the county page. 3. Email, fax, or mail the application package to the county. The county expressly directs that all permit applications be emailed to garagon@upsoncountyga.org. 4. Deliver hard-copy construction plans to the Building and Zoning office. The county states plans must be hard copies, 36x24 or larger, and will not accept construction plans by email. 5. Submit the required supporting materials. The county's published new-construction requirements call for project value, contractor and subcontractor information, power provider, map and parcel data, acreage, physical address, site plan, zoning and floodplain information, two sets of plans, and as applicable COMcheck, erosion permit, driveway certificate of compliance, septic permit, well permit, homeowner checklist, and homeowner affidavit. 6. Wait for county review and permit processing. The county page states staff will get in touch after the permit has been processed. 7. Schedule and complete required inspections through the county program before final approval and occupancy.
03 How do I schedule a building inspection in unincorporated Upson County, GA?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in unincorporated Upson County, GA via: 706-647-1297.
last verified April 2026 source Upson County Building and Zoning Department ↗ entry id permits/georgia/upson/unincorporated

Educational reference. Permit rules and fees change — confirm current requirements directly with Upson County Building and Zoning Department before applying. Jaspector is not legal advice.