City of Smyrna

How to apply for a building permit in City of Smyrna, Georgia. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

Building Division, Community Development, City of Smyrna

Street address
3180 Atlanta Rd SE, Smyrna, GA 30080
Coverage
Applies within Smyrna city limits only.
Online portal
OpenGov Portal
OpenGov
§ 02

When a permit is required

Permit triggers and exempt work for Smyrna

New homes, decks, reroofs, windows, interior remodels, additions, accessory structures over 200 square feet or over one story for residential work, retaining walls, pools, solar, generators, projects involving two or more licensed trades, structural and interior demolition, mechanical replacements, tree removals of 24 inches or larger, and land disturbance.

Note: No standalone public exempt-work list was located on the reviewed Smyrna pages. The city publishes detailed permit-required lists and directs applicants to use the portal or call when in doubt.

Required documents
  • Building permit application in the portal
  • Supplemental plans
  • Documents and licenses as required by permit type
Building code
Smyrna follows the current Georgia state minimum standard construction codes adopted by DCA and enforces them through local administrative procedures. Code changes effective January 1, 2026.
Permit validity
Building permits are valid for six months if there is no activity.
Owner-builder
A homeowner may obtain a building permit only if the property is the homeowner's current permanent residence and is in the homeowner's legal name. A landlord may not do rental-house work unless Georgia-licensed.
Contractor requirements
The city ensures contractors are properly licensed and permitted. Georgia state contractor licensing rules apply.
§ 03

Application process

Typical processing: Residential plan review typically 5 to 10 business days; commercial typically 2 to 3 weeks; land disturbance typically 4 to 5 weeks.

  1. 01
    Create an account in the Smyrna online portal.
  2. 02
    Select the permit type and upload all plans, licenses, and supporting documents required for that scope.
  3. 03
    Submit through the portal; in-person submittals are not accepted.
  4. 04
    The city performs plan review, routing to other departments as needed.
  5. 05
    Pay permit fees in the portal.
  6. 06
    After issuance, schedule inspections in the same portal and obtain CO or completion documents after finals.

Typical processing time: Residential plan review typically 5 to 10 business days; commercial typically 2 to 3 weeks; land disturbance typically 4 to 5 weeks.

Source: Building Division, Community Development, City of Smyrna ↗

§ 04

Fee schedule

Smyrna building permit fees

Fee type
Amount
01
Minimum permit fee
$125 minimum building permit fee; $65 minimum standalone permit fee
02
Plan check fee
Commercial plan review fee $350; townhome plan review fee $50 per lot; Fire Marshal plan review fees separate.
03
Permit fee formula
Building and land disturbance permits are $7 per $1,000 of estimated construction cost, plus 10 percent records fee and $15 technology fee.
04
Trade permit fee
Standalone MEP permits are flat-fee based.
05
Reinspection fee
Reinspection fees are $50 first, $100 second, $150 third, $200 fourth and above.
06
Penalty (no permit)
Work without permit can trigger added fees and enforcement.

Fees are paid through the OpenGov portal. Separate water, sewer, and fire fees may apply through other offices.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
Scheduling deadline
Requests received by 4:00 PM are scheduled for the next business day; requests after 4:00 PM or on weekends are scheduled two business days out.

Typical sequence: Required inspections are identified during plan review and listed on the permit. Final inspections lead to CO or certificate of completion depending on project type.

§ 06

Frequently asked

Common questions about Smyrna permits

01 Do I need a building permit in Smyrna, GA?
New homes, decks, reroofs, windows, interior remodels, additions, accessory structures over 200 square feet or over one story for residential work, retaining walls, pools, solar, generators, projects involving two or more licensed trades, structural and interior demolition, mechanical replacements, tree removals of 24 inches or larger, and land disturbance.
02 How much does a building permit cost in Smyrna, GA?
Building permit fees in Smyrna, GA are set by the local building department and vary by project type and valuation. The minimum permit fee is $125 minimum building permit fee; $65 minimum standalone permit fee. Fees are calculated as: Building and land disturbance permits are $7 per $1,000 of estimated construction cost, plus 10 percent records fee and $15 technology fee.. Plan check fee: Commercial plan review fee $350; townhome plan review fee $50 per lot; Fire Marshal plan review fees separate..
03 How do I apply for a building permit in Smyrna, GA?
To apply for a building permit in Smyrna, GA, follow these steps: 1. Create an account in the Smyrna online portal. 2. Select the permit type and upload all plans, licenses, and supporting documents required for that scope. 3. Submit through the portal; in-person submittals are not accepted. 4. The city performs plan review, routing to other departments as needed. 5. Pay permit fees in the portal. 6. After issuance, schedule inspections in the same portal and obtain CO or completion documents after finals.
04 How long does it take to get a building permit in Smyrna, GA?
Building permit processing times in Smyrna, GA typically run Residential plan review typically 5 to 10 business days; commercial typically 2 to 3 weeks; land disturbance typically 4 to 5 weeks.. Timelines can vary based on project complexity and current department workload.
05 How do I schedule a building inspection in Smyrna, GA?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Smyrna, GA via: OpenGov Portal. Requests received by 4:00 PM are scheduled for the next business day; requests after 4:00 PM or on weekends are scheduled two business days out..
last verified April 2026 source Building Division, Community Development, City of Smyrna ↗ entry id permits/georgia/cobb/smyrna

Educational reference. Permit rules and fees change — confirm current requirements directly with Building Division, Community Development, City of Smyrna before applying. Jaspector is not legal advice.