jaspector
§ CO Adams County
City building permits

City of Brighton

How to apply for a building permit in City of Brighton, Colorado. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

City of Brighton Community Development, Building Permitting Division

Street address
500 S. 4th Avenue, Brighton, CO 80601
Coverage
Brighton issues permits within Brighton city limits, including the Adams County portion of the city.
Online portal
OpenGov
OpenGov
§ 02

When a permit is required

Permit triggers and exempt work for Brighton

Brighton requires permits for regulated building work; emergency repairs and replacements for water heaters, heating systems, and water or sewer services can proceed first but the permit application must be made by the next business day and the work cannot be concealed.

Note: Brighton's public permit page reviewed did not include a single consolidated exemption list. Confirm exemptions with the Building Permit Counter before proceeding without a permit.

Required documents
  • Online application
  • Plan set
  • Permit card
  • Project-specific submittals
  • Contractor-license documentation where required
Building code
Brighton municipal code Chapter 15 and current permit materials indicate city-adopted building and trade codes; verify exact current code package by permit date with the Building Official.
Permit validity
Not clearly summarized on the public permit page reviewed.
Owner-builder
Brighton code excerpts state an owner may perform work on his or her own personal residence and accessory buildings, but may construct only one personal residence within three consecutive years under that exception.
Contractor requirements
Brighton requires contractor licenses for general, mechanical, plumbing, and electrical contractors; applicants sign up in OpenGov and pay the required application fees; insurance is required.

Source: City of Brighton Community Development, Building Permitting Division ↗

§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Create an OpenGov account for permits or contractor licensing.
  2. 02
    Select the permit type and complete the online application.
  3. 03
    Upload stamped plans, permit documents, and any supporting trade or site materials.
  4. 04
    Respond to plan-review comments and provide any missing materials.
  5. 05
    Pay fees through the portal.
  6. 06
    Print the approved stamped plans and permit card from the portal and keep them on site for inspections.

Source: City of Brighton Community Development, Building Permitting Division ↗

§ 04

Fee schedule

Brighton building permit fees

Fee type
Amount
01
Minimum permit fee
$23.50 for valuation from $1 to $500
02
Plan check fee
65 percent of permit fee
03
Permit fee formula
Valuation-based building permit fee schedule plus plan review fees, use tax, and other adopted charges.
04
Penalty (no permit)
$350 review fee for change orders in land-use development materials

Fees are paid through OpenGov; plans and permit cards must then be printed from the portal.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • Portal (online)
  • Homeowner Inspection Line 303-655-2151 (phone)
  • General inspection questions 303-655-2017 (phone)
Scheduling deadline
Requests should be made before 4:00 p.m. for next-business-day inspection when available.
Inspection hours
For arrival windows call between 8:00 a.m. and 8:30 a.m. on inspection day; city hall and Community Development close at noon on Fridays.

Typical sequence: Permit issuance, staged inspections before concealment, final inspection, and CO where applicable.

Source: City of Brighton Community Development, Building Permitting Division ↗

§ 06

Frequently asked

Common questions about Brighton permits

01 Do I need a building permit in Brighton, CO?
Brighton requires permits for regulated building work; emergency repairs and replacements for water heaters, heating systems, and water or sewer services can proceed first but the permit application must be made by the next business day and the work cannot be concealed.
02 How much does a building permit cost in Brighton, CO?
Building permit fees in Brighton, CO are set by the local building department and vary by project type and valuation. The minimum permit fee is $23.50 for valuation from $1 to $500. Fees are calculated as: Valuation-based building permit fee schedule plus plan review fees, use tax, and other adopted charges.. Plan check fee: 65 percent of permit fee.
03 How do I apply for a building permit in Brighton, CO?
To apply for a building permit in Brighton, CO, follow these steps: 1. Create an OpenGov account for permits or contractor licensing. 2. Select the permit type and complete the online application. 3. Upload stamped plans, permit documents, and any supporting trade or site materials. 4. Respond to plan-review comments and provide any missing materials. 5. Pay fees through the portal. 6. Print the approved stamped plans and permit card from the portal and keep them on site for inspections.
04 How do I schedule a building inspection in Brighton, CO?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Brighton, CO via: Portal, Homeowner Inspection Line 303-655-2151, General inspection questions 303-655-2017. Requests should be made before 4:00 p.m. for next-business-day inspection when available..
last verified April 2026 source City of Brighton Community Development, Building Permitting Division ↗ entry id permits/colorado/adams/brighton