jaspector
City building permits

Town of Clifton

How to apply for a building permit in Town of Clifton, Arizona. Permit authority, application steps, fees, and inspection requirements.

Code adoption
2009 International Building Code
Last verified
April 2026
On this page 6
§ 01

Permit authority

Building Department / Code Enforcement

Street address
Town Hall, 510 Coronado Boulevard, Clifton, AZ 85533
Coverage
All properties within the incorporated Town of Clifton.
Additional resources
§ 02

When a permit is required

Permit triggers and exempt work for Clifton

A building permit is required for any construction, alteration, repair, or demolition within the Town of Clifton unless the work falls within listed exemptions.

Storage structures not over 200 square feet
Fences not over 6 feet in height
Retaining walls not over 4 feet
Sidewalks and driveways
Painting, papering, tiling, carpeting, cabinets, countertops, and similar finish work
Certain window awnings
Decks not over 200 square feet and not more than 30 inches above grade
Portable heating, ventilation, or cooling units
Replacement of minor parts that do not alter equipment approval or make equipment unsafe
  • Exempt Storage structures not over 200 square feet
  • Exempt Fences not over 6 feet in height
  • Exempt Retaining walls not over 4 feet
  • Exempt Sidewalks and driveways
  • Exempt Painting, papering, tiling, carpeting, cabinets, countertops, and similar finish work
  • Exempt Certain window awnings
  • Exempt Decks not over 200 square feet and not more than 30 inches above grade
  • Exempt Portable heating, ventilation, or cooling units
  • Exempt Replacement of minor parts that do not alter equipment approval or make equipment unsafe

Note: Exempt from building permit does not mean exempt from other town requirements or codes. Confirm edge cases with the Building Department before proceeding.

Required documents
  • Completed building permit application
  • Site plan (scaled)
  • Footing and foundation plan
  • Floor plan
  • Framing plans
  • Elevations
  • Electrical plans
  • Plumbing information
Building code
2009 International Building Code

Source: Building Department / Code Enforcement ↗

§ 03

Application process

Typical processing: Varies; consult with Building Inspector for specific project timeline.

  1. 01
    Review Clifton's exempt work categories and determine if your project requires a building permit.
  2. 02
    Download the residential permit checklist and building permit application from the town website.
  3. 03
    Prepare all required scaled drawings including site plan, footing and foundation plan, floor plan, framing plans, elevations, electrical plans, and plumbing information.
  4. 04
    Create a MyGov account and submit permit application with all required documents online.
  5. 05
    Town staff reviews the application for completeness and permits.
  6. 06
    Contact the Building Inspector at least two days before inspections are needed.
  7. 07
    Receive permit approval and proceed with construction.

Typical processing time: Varies; consult with Building Inspector for specific project timeline.

Source: Building Department / Code Enforcement ↗

§ 04

Fee schedule

Clifton building permit fees

Fee type
Amount
01
Permit fee formula
Consult with town for current building permit fees and plan review charges.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • (928) 322-7913 (phone)
Scheduling deadline
Notify building inspector at least two days before inspection is needed.
Inspection hours
Monday through Thursday, 7:00 AM to 5:00 PM

Source: Building Department / Code Enforcement ↗

§ 06

Frequently asked

Common questions about Clifton permits

01 Do I need a building permit in Clifton, AZ?
A building permit is required for any construction, alteration, repair, or demolition within the Town of Clifton unless the work falls within listed exemptions.
02 How much does a building permit cost in Clifton, AZ?
Building permit fees in Clifton, AZ are set by the local building department and vary by project type and valuation. Fees are calculated as: Consult with town for current building permit fees and plan review charges..
03 How do I apply for a building permit in Clifton, AZ?
To apply for a building permit in Clifton, AZ, follow these steps: 1. Review Clifton's exempt work categories and determine if your project requires a building permit. 2. Download the residential permit checklist and building permit application from the town website. 3. Prepare all required scaled drawings including site plan, footing and foundation plan, floor plan, framing plans, elevations, electrical plans, and plumbing information. 4. Create a MyGov account and submit permit application with all required documents online. 5. Town staff reviews the application for completeness and permits. 6. Contact the Building Inspector at least two days before inspections are needed. 7. Receive permit approval and proceed with construction.
04 How long does it take to get a building permit in Clifton, AZ?
Building permit processing times in Clifton, AZ typically run Varies; consult with Building Inspector for specific project timeline.. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Clifton, AZ?
Not all construction work requires a permit in Clifton, AZ. The following work is generally exempt: Storage structures not over 200 square feet; Fences not over 6 feet in height; Retaining walls not over 4 feet; Sidewalks and driveways; Painting, papering, tiling, carpeting, cabinets, countertops, and similar finish work; Certain window awnings; Decks not over 200 square feet and not more than 30 inches above grade; Portable heating, ventilation, or cooling units; Replacement of minor parts that do not alter equipment approval or make equipment unsafe. Note: Exempt from building permit does not mean exempt from other town requirements or codes. Confirm edge cases with the Building Department before proceeding. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Clifton, AZ?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Clifton, AZ via: (928) 322-7913. Notify building inspector at least two days before inspection is needed..
last verified April 2026 source Building Department / Code Enforcement ↗ entry id permits/arizona/greenlee/clifton

Educational reference. Permit rules and fees change — confirm current requirements directly with Building Department / Code Enforcement before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Greenlee County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Greenlee County jurisdictions →