City Building Permits

Newman, CA Building Permit Guide

How to apply for a building permit in Newman, California. Permit authority, application steps, fees, and inspection requirements.

California Stanislaus County Updated March 2026

Permit Authority

City of Newman municipal permits.

Department
Building Department, City of Newman
Address
938 Fresno Street, Newman, CA 95360
Phone
209-862-3725 (option 8)

Online Permit Portal

Platform: E-Docs document library + Symbium for qualifying residential solar • Account required: No • Submission: Online or in-person

Application Process

  1. Download the correct application from Building Department E-Docs for the project type.
  2. Complete the form legibly and accurately, including contact information and permit details.
  3. Submit the permit application in person at City Hall or by email, using the address listed on the application header.
  4. City staff issues an invoice after a complete package is received for over-the-counter projects; plan check projects go through review.
  5. If plan check is required, review is typically around 10 days, depending on workload and project type.
  6. Pay the invoice by card or check; phone payments are not accepted.
  7. Schedule inspections and proceed through the required inspection sequence.

Typical processing time: Plan checks usually take about 10 days.

Source: Building Department, City of Newman

General Requirements

Examples include patio covers, new rear sheds over 120 square feet, swimming pools, house additions, reroofing, HVAC new or replacement work, water heaters, water softeners, plumbing beyond minor repairs or clearing stoppages, and all electrical projects except receptacle or fixture replacement.

Required Documents

  • Completed building permit application
  • Supporting project details and permits applicable to the project
  • Contractor name and license information
  • Signed contractor declaration when applicable
  • Owner-builder declaration if the owner is acting as builder
  • ESCP for soil-disturbance projects
  • Planning Department approval for ADUs before permit submission
Permit validity
Permits expire 12 months from issue date.
Building code
California Building Code - 2025 Edition of Title 24 Part 2 Volume 1 and 2, with city additions and amendments.
Owner-builder
Owner-builder permits are allowed, but require the owner-builder declaration and acknowledgment.
Contractor requirements
Building permit application includes licensed contractor declaration and workers' compensation statements. Contractors are expected to be licensed and bonded per California law.

Fees

Minimum permit fee
$118
Plan check fee
65% of permit fee unless specified otherwise for a project type. Expedited plan check is doubled.
Permit fee formula
Valuation-based and square-footage tables for most building types, often shown as a base charge plus permit processing and inspection components.
Reinspection fee
$145 per hour cost recovery for reinspection or investigation
Penalty (no permit)
Additional plan review is also listed at $145 per hour.
Payment note
No phone payments accepted; payment is by in-person card or check, and checks may be mailed to P.O. Box 787, Newman, CA 95360.

Fees change. Verify current amounts at the official fee schedule.

Work That Does NOT Require a Permit

  • Window and door retrofit work when no framing is needed and no paper is exposed
  • Receptacle or fixture replacement in electrical work
  • Minor plumbing repairs and clearing stoppages
  • Sheds under 120 square feet generally require a zoning permit, not a building permit

Important: The city list is non-exhaustive and subject to change. If uncertain, call the Building Department before starting work.

Inspections

How to Schedule

  • 209-862-3725 option 8 (phone)
  • buildingdepartment@cityofnewman.gov (email)
Scheduling deadline
Inspections can be scheduled at least 1 day to no more than 1 week out.
Inspection hours
Monday-Thursday, 8:00 AM-12:00 PM and 1:00 PM-5:00 PM.
Time windows
8:00 AM-12:00 PM or 1:00 PM-5:00 PM

Typical inspection sequence: Typical sequence includes foundation, shear or roof nailing, frame inspection, plumbing and mechanical at time of inspection, electrical, plumbing, mechanical, gypsum or lath, T-bar ceiling, insulation, and miscellaneous inspection.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Building Department, City of Newman before applying.

Need help with your project?

Navigating permits in Newman can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.

Other cities in Stanislaus County

View all Stanislaus County jurisdictions →