City Building Permits
Pismo Beach, CA Building Permit Guide
How to apply for a building permit in Pismo Beach, California. Permit authority, application steps, fees, and inspection requirements.
Permit Authority
City permits and inspections for projects in the City of Pismo Beach.
- Department
- City of Pismo Beach, Building Division
- Address
- 760 Mattie Road, Pismo Beach, CA 93449
- Phone
- 805-773-7040
Online Permit Portal
Platform: Public Portal • Account required: No • Submission: Online only
Additional resources:
Application Process
- Before submitting a building application, determine whether the project changes the building footprint, changes use of space, or adds exterior changes.
- If any of those answers are yes, obtain planning approval before the building submittal.
- Prepare the completed permit application, complete plan set, and supporting reports.
- Submit separate PDF files for plans, application materials, and supporting documents as required by the checklist.
- Pay the plan review fee after city processing and before review starts.
- Proceed through review under the applicable code cycle and vesting rules.
- Fully process and obtain the permit within 365 days of application submission or resubmit as a new package.
General Requirements
Required Documents
- Completed application
- Owner-builder acknowledgment and any required owner-builder agent authorization
- Copy of planning permit conditions if applicable
- Stamped and signed plan set where required, including title sheet, site plan, floor plans, electrical, mechanical, plumbing, and structural plans, and supporting calculations
- Title 24 compliance documentation
- Required soils report for projects of 500 square feet or more
- Drainage report
- Permit validity
- Building permits must be fully processed and permitted within 365 days of application submission or a new full resubmittal is required.
- Building code
- Applications with plan-check fees paid on or after January 1, 2026 are under the 2025 codes. Earlier vested applications may remain under the 2022 codes if vesting deadlines and plan check conditions are met.
- Owner-builder
- Owner-builder acknowledgment and owner-builder agent authorization may be required.
Fees
- Minimum permit fee
- $82.87 for valuation from $1 to $500
- Plan check fee
- Plan review is separate and calculated at 100% of building permit fee components. Plan review fees must be paid before routing for review.
- Permit fee formula
- Representative building permit tiers include $82.87 for valuation from $1 to $500, then increasing tiered charges by valuation bracket, including $8.27 per additional $100 from $501 to $2,000 and $35.93 per additional $1,000 in higher brackets.
- Reinspection fee
- $30 when the applicant is not ready for a scheduled inspection
- Payment note
- Permit-related fees are processed online through the city's official payments site.
Fees change. Verify current amounts at the official fee schedule (effective January 1, 2026).
Work That Does NOT Require a Permit
- Some signs are exempt from permit requirements, including examples where planning permit is not required, temporary sale or rental signs, and signs by transportation authorities
Important: The city does not publish one universal exempt-work list for building permits in the cited sources. Separate sign requirements still apply, and sign projects should be verified for planning and building impacts before they are treated as exempt.
Inspections
How to Schedule
- 805-773-7045 (phone)
- On-site inspection request form (online)
- Scheduling deadline
- Calls received by 7:00 AM may receive same-day inspections.
- Time windows
- Inspections are generally by appointment. Engineering appointment times are typically 8:30 AM to 4:00 PM, and cancellations require at least 1 hour prior notice.
Typical inspection sequence: Applicants must pass required inspections before project finalization.
Additional Resources
- Building code: Applications with plan-check fees paid on or after January 1, 2026 are under the 2025 codes. Earlier vested applications may remain under the 2022 codes if vesting deadlines and plan check conditions are met.
- Building permit checklist
- Building codes and transition notes
- Campaign signs and sign exemptions
- License lookup guide: California Contractor License Requirements
- Contract template: California Homeowner-Contractor Agreement
Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the City of Pismo Beach, Building Division before applying.
Need help with your project?
Navigating permits in Pismo Beach can be complicated.
Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.
Learn how Jaspector worksOther cities in San Luis Obispo County