Permit Authority

For properties inside Nevada City limits, applicants first submit the required city planning or architectural review application to Nevada City. If the project also requires a building permit, the applicant then submits the city-approved plans to the Nevada County Building Department, which performs building plan review, permit issuance, and inspections for the City by contract.

Department
City of Nevada City Planning Department for local planning and architectural review; Nevada County Community Development Agency, Building Department for building permit issuance and inspections under contract to the City
Address
City of Nevada City Planning Department, 317 Broad Street, Nevada City, CA 95959; Nevada County Building Department, 950 Maidu Avenue, Suite 170, Nevada City, CA 95959-7902
Phone
City Planning (530) 265-2496; Nevada County Building Department (530) 265-1222 Option 1

Online Permit Portal

Platform: Accela Citizen Access (ACA) / Citizen Access Portal • Account required: Yes • Submission: Online or in-person

Application Process

  1. Confirm the Nevada City entitlement path first and choose the correct planning form and supporting documents.
  2. Submit the required Nevada City planning or architectural review application in person at City Hall or by email to the City Planner.
  3. Pay the Nevada City planning fee. The City says the project will not be reviewed until the fee is paid.
  4. After City approval, submit the city-approved plans to the Nevada County Building Department if the project requires a building permit.
  5. Provide the building submittal package and pay plan check fees. County materials call for the permit application plus project documents such as plans, site plan, engineering or truss calculations where applicable.
  6. Respond to corrections and obtain outside clearances as needed.
  7. Receive the permit, keep the approved plans on site, and schedule required inspections through the county inspection system as construction progresses.

Typical processing time: Nevada City does not publish a standard planning review timeline on the pages reviewed. Nevada County publishes an Over-the-Counter Wednesday process for qualifying minor projects by appointment; otherwise, no universal countywide turnaround is posted on the main permit pages reviewed.

Source: City of Nevada City Planning Department for local planning and architectural review; Nevada County Community Development Agency, Building Department for building permit issuance and inspections under contract to the City

General Requirements

Applicants within city limits must first obtain City approval, then submit city-approved plans to Nevada County if the project requires a building permit. County materials require a permit before constructing, enlarging, altering, repairing, moving, demolishing, or changing occupancy of a building or structure, and before installing or altering regulated electrical, gas, mechanical, or plumbing systems.

Required Documents

  • Appropriate Nevada City planning form
  • Necessary supporting documentation
  • Site plan checklist
  • Agent authorization letter if acting for the owner
  • Sewer backflow prevention confirmation for building permits where applicable
  • Building permit application
  • Plan sets
  • Site plans
  • Truss calculations where applicable
  • Engineering calculations where applicable
  • Outside-agency approvals or receipts where required
Permit validity
Nevada County materials state the permit expires 12 months from issuance or 12 months from the last passing inspection. The county handbook also says permits are active for one year from issuance and may be eligible for a one-year extension for justifiable cause if requested before expiration. The county application form separately states permitted work must be completed within 2 years of issuance.
Building code
All construction projects submitted on or after January 1, 2026 must comply with the 2025 California Building Standards Code, including current Energy Codes, plus Nevada County local amendments effective January 1, 2026. Nevada City relies on Nevada County for building code enforcement under the City contract arrangement.
Owner-builder
Nevada County application materials include an Owner-Builder Declaration and require the applicant to select the applicable owner-builder basis under penalty of perjury.
Contractor requirements
Nevada County application materials require the applicant to affirm California contractor license status when acting as contractor and include workers' compensation declarations required by California law.

Fees

Minimum permit fee
Nevada City planning fees start at $120 for minor like-for-like architectural review and $120 for certain change-of-occupancy or sign-review items. On the county side, FY 25-26 building fees show $92.74 for OTC permit processing and $185.48 for non-OTC permit processing, both in addition to applicable inspection, plan review, state, and other local charges.
Plan check fee
Nevada City charges separate planning review fees where applicable, such as $120 for Plan Check (other), $240 for generator plan check, and percentage-based grading plan check items. Nevada County plan review fees vary by occupancy and square footage; for example, code 221 for site-built residences is $975.62 plus $0.03 per square foot and includes one plan recheck.
Permit fee formula
Mixed. Nevada City uses flat fees or deposits by entitlement type. Nevada County uses a combination of administrative flat fees, hourly-rate fees, and use- or square-footage-based building inspection and plan review formulas.
Reinspection fee
Nevada County FY 25-26 fees list reinspection under code B114 at $185.48. Reinspection fees must be paid before another inspection will be scheduled.
Penalty (no permit)
Nevada City FY 25-26 fees include after-the-fact permit pricing at $230 plus staff time and management cost for permits without a listed fee, or 2x permit fee plus staff time and management cost for permits with a listed fee. The City also has a general late submission charge of $25 or 15%, whichever is higher, where no specific late charge is set.
Payment note
Nevada City planning fees may be paid in person at City Hall or online through the City Paystar payment portal. Nevada County also links online building payments through LexisNexis.

Fees change. Verify current amounts at the official fee schedule (effective July 1, 2025).

Work That Does NOT Require a Permit

  • One-story detached accessory structures up to 120 square feet; Nevada County also notes one 200 square foot one-story detached accessory structure
  • Fences not over 7 feet high
  • Retaining walls not over 4 feet high unless supporting a surcharge
  • Water tanks supported directly on grade if capacity does not exceed 5,000 gallons and the height-to-diameter or width ratio does not exceed 2:1
  • Sidewalks and driveways
  • Painting, papering, tiling, carpeting, cabinets, countertops, and similar finish work
  • Prefabricated swimming pools less than 24 inches deep
  • Swings and other playground equipment
  • Window awnings meeting the County dimensional and support limits
  • Detached decks not over 200 square feet, not more than 30 inches above grade, not attached to a dwelling, and not serving the required exit door
  • Minor electrical work such as listed cord-and-plug temporary decorative lighting, like-kind overcurrent device replacement, and low-voltage work under the County posted thresholds
  • Minor gas, mechanical, and plumbing work listed on the County exemption page, including certain portable equipment, minor-part replacements, stopping leaks, and clearing stoppages where piping, valves, or fixtures are not replaced or rearranged

Important: Nevada County states that if a project is not on its exemption list, a permit is required. Exemptions do not remove the need to comply with code or other laws. Within Nevada City, separate city planning or architectural review may still be required even where the County building permit exemption list applies.

Inspections

How to Schedule

Scheduling deadline
Next-working-day inspections must be requested by 12:00 a.m. midnight. For cancellations, call by 8:00 a.m. on inspection day.
Inspection hours
Building Department public hours are Monday through Friday, 8:00 a.m. to 5:00 p.m. Nevada City is served in the western county inspection area, which operates Monday through Friday.
Time windows
Today's two-hour inspection window is posted online by 8:00 a.m. on inspection day.

Typical inspection sequence: The exact inspection sequence depends on permit type and approved plans. County examples include foundation and final for many simple permits; deck and final for reroofs; footing and final for fences over 7 feet; foundation and grout lifts for masonry retaining walls; forms, footing, and wall for concrete retaining walls; and final inspection for permit completion. Larger projects typically include foundation or under-slab stages, framing and rough trade stages, insulation or cover stages where applicable, and final.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the City of Nevada City Planning Department for local planning and architectural review; Nevada County Community Development Agency, Building Department for building permit issuance and inspections under contract to the City before applying.

Need help with your project?

Navigating permits in Nevada City can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.

Other cities in Nevada County

View all Nevada County jurisdictions →