Permit Authority

Applies to properties within the City of Dos Palos city limits. Use the city's GIS and Land Use Mapping Locator to confirm jurisdiction. Work in the public right-of-way also requires a separate city encroachment permit.

Department
City of Dos Palos Community Development Department, Building Division / Building Department
Address
2174 Blossom Street, Dos Palos, CA 93620
Phone
(209) 392-2174

Online Permit Portal

Platform: Municipal website forms library for standard permits • Account required: No • Submission: Online or in-person

Application Process

  1. Confirm the parcel is inside Dos Palos city limits and verify zoning or land-use constraints using the city's GIS and zoning resources.
  2. Complete the City of Dos Palos building permit application with owner and contractor information, contractor license data, business license data, valuation, square footage, APN, occupancy or use, and planning review fields.
  3. Assemble plans and supporting documents, including the city's minimum site-plan requirements and any trade-specific or project-specific forms.
  4. Submit the application package to the city. The city does not publish a separate online workflow for ordinary building permits; qualifying residential solar permits may be submitted through Symbium.
  5. Pay permit and related fees once calculated by the city.
  6. Obtain required inspections during construction and provide required site access.

Source: City of Dos Palos Community Development Department, Building Division / Building Department

General Requirements

City materials show permits are used for new construction and typical building or trade work such as new fences, garage enclosures, reroofs, photovoltaics, water heaters, electrical, plumbing, and mechanical work.

Required Documents

  • Completed building permit application
  • Plans drawn to scale
  • Site plan with APN and address
  • Setbacks and structures information
  • Access and parking information
  • Utilities information
  • Project-specific supporting forms
  • Flood information or flood certificate where required
  • Contractor licensing and workers' compensation declarations or owner-builder declaration
Building code
2022 California Building Code, Residential Code, Electrical Code, Mechanical Code, Plumbing Code, Energy Code, Fire Code, Green Standards Code, Existing Building Code, and related Title 24 codes
Owner-builder
The city application includes an owner-builder declaration covering licensed-contractor work, split responsibility arrangements, or owner-performed work for structures not intended or offered for sale.
Contractor requirements
The application requires contractor license number, class, expiration date, a signed licensed-contractor declaration, and workers' compensation information. Contractors doing business in the city must also hold a city business license.

Fees

Plan check fee
Shown as a separate line item on the application form, but no public amount or formula was found.
Permit fee formula
The city application requires project valuation and lists separate fee buckets for building permit, plan check, PME, planning, SMI, city or county impact fees, and the SB 1473 green fee, indicating a mixed fee structure.
Reinspection fee
A reinspection fee may be issued if a second inspection request is canceled for lack of required access.
Payment note
The application states additional fees may be required and directs applicants to contact the city for more information. For Symbium solar permits, the city issues the permit after the applicant pays the city's permit fee invoice.

Work That Does NOT Require a Permit

Contact the City of Dos Palos Community Development Department, Building Division / Building Department to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

  • (209) 392-2174 (phone)
  • communitydevelopment@cityofdp.com (email)
Inspection hours
City Hall and Community Development hours are Monday-Friday, 8:00 AM to 4:30 PM. Some pages also note phone availability from 8:00 AM to 4:00 PM.

Typical inspection sequence: The city publishes a reroof inspection sequence including deck inspection after removal of built-up roofing, nailing inspection after new plywood or OSB sheathing, final inspection after completion, and inspection of any roof-mounted equipment covered by the permit. Other project inspection sequences depend on scope.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the City of Dos Palos Community Development Department, Building Division / Building Department before applying.

Need help with your project?

Navigating permits in Dos Palos can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.

Other cities in Merced County

View all Merced County jurisdictions →