On this page 5
When a permit is required
Permit triggers and exempt work for Roane County
A building permit is required for new construction, additions, structural alterations, demolition, interior/exterior remodeling, land disturbing activities (1 acre or greater), septic system installation, and any work valued at $2,500 or more.
- Exempt Agricultural buildings or structures utilized primarily for agricultural purposes (exempt from West Virginia State Building Code, State Fire Code, and county building code requirements)
Note: Agricultural exemption does not apply to tax, utility, and service obligations. Confirm exemption status with County Clerk before proceeding.
- Completed permit application
- Site survey and location outline
- Building plans and specifications
- Proof of property ownership or authorization
- Building code
- West Virginia State Building Code (effective July 1, 2025)
- Contractor requirements
- Contractors performing work valued at $2,500 or more must be licensed by the West Virginia Contractor Licensing Board (WVCLB).
Application process
Typical processing: 4 weeks or less
- 01 Contact the County Clerk to determine permit requirements for your specific project.
- 02 Complete the appropriate application form (available from County Clerk).
- 03 Provide required documentation (site survey, plans, specifications).
- 04 Submit application with applicable fees to the County Clerk's office.
- 05 Wait for county review (typically 4 weeks or less).
- 06 Receive approval or notification of required changes.
- 07 Pay remaining fees upon approval.
- 08 Display project notice/sign if required.
- 09 Schedule required inspections before, during, and after construction.
Typical processing time: 4 weeks or less
Required inspections
Scheduling and sequence
- County Clerk's Office (phone)
- 200 Main Street, Spencer, WV 25276 (in-person)
- Inspection hours
- Monday–Friday, 8:30 AM–4:00 PM
Typical sequence: Required inspection stages: foundation/footings (before concrete pour), framing (after structural framing completion), rough utilities (electrical, plumbing, HVAC before wall closure), final inspection (after all work complete and code-compliant), occupancy inspection (before occupancy).
Frequently asked
Common questions about unincorporated Roane County permits
01 Do I need a building permit in unincorporated Roane County, WV? ▸
02 How do I apply for a building permit in unincorporated Roane County, WV? ▸
03 How long does it take to get a building permit in unincorporated Roane County, WV? ▸
04 What work is exempt from building permits in unincorporated Roane County, WV? ▸
05 How do I schedule a building inspection in unincorporated Roane County, WV? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Roane County Clerk's Office before applying. Jaspector is not legal advice.