How to apply for a building permit in City of Raymond, Washington. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

Public Works — Building and Development Division

Street address
City Hall, 230 Second Street, Raymond, WA 98577
Coverage
All properties within the incorporated City of Raymond.
Online portal
Building & Development Forms
Paper/Email Submission
§ 02

When a permit is required

Permit triggers and exempt work for Raymond

A building permit is required for all construction projects within the City of Raymond.

Fences 6 feet or shorter in height
Sheds and outbuildings 10 feet by 12 feet or smaller, with no permanent foundation, plumbing, or electrical connections
Residential re-roofing
Woodstove or heat pump installations (Mechanical Permit required)
  • Exempt Fences 6 feet or shorter in height
  • Exempt Sheds and outbuildings 10 feet by 12 feet or smaller, with no permanent foundation, plumbing, or electrical connections
  • Exempt Residential re-roofing
  • Exempt Woodstove or heat pump installations (Mechanical Permit required)

Note: Commercial re-roofing or roofing affecting the structural integrity of a building requires a permit. Confirm edge cases with the Building and Development Division before proceeding.

Required documents
  • Completed permit application
  • Site plan
  • Construction drawings (scale required)
  • Project scope information
  • Proof of property ownership or authorization
  • Itemized response letter for any resubmittals
Building code
International Building Code and International Residential Code with Washington State amendments.
Permit validity
Permits expire if work does not begin within 180 days of issuance. Building inspector issues written notice of expiration.
Owner-builder
Owner-builders may self-perform work on owner-occupied properties under certain conditions; confirm with Building and Development Division.
Contractor requirements
All contractors must be registered with Washington State Department of Labor and Industries (L&I). Verify contractor registration at https://secure.lni.wa.gov/verify/ before engagement.

Source: Public Works — Building and Development Division ↗

§ 03

Application process

Typical processing: Timeframe varies; direct contact with Building Permit Tech required for current schedule.

  1. 01
    Download the Building Packet or appropriate application form from the city website Forms page.
  2. 02
    Complete the application with all required supporting documents (site plan, construction drawings).
  3. 03
    Submit application to Tia Channell via email (tchannell@cityofraymond.com) or in person at City Hall.
  4. 04
    Pay applicable fees in person or via InvoiceCloud online portal at time of submittal.
  5. 05
    Building Inspector schedules review of submitted materials.
  6. 06
    Schedule required inspections through Tia Channell during business hours (Monday–Thursday, 7:30 AM–4:00 PM).
  7. 07
    Complete all required inspections before proceeding to next phase.
  8. 08
    Receive final approval; structure may not be occupied until final inspection sign-off.

Typical processing time: Timeframe varies; direct contact with Building Permit Tech required for current schedule.

Source: Public Works — Building and Development Division ↗

§ 04

Fee schedule

Raymond building permit fees

Fee type
Amount
01
Permit fee formula
Set by City resolution; contact Tia Channell (360-942-4122) or tchannell@cityofraymond.com for current fee schedule.

Fees due at time of submittal. Payment accepted in person at City Hall or via InvoiceCloud online portal.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • Tia Channell, Building Permit Tech: (360) 942-4122 (phone)
  • tchannell@cityofraymond.com (email)
Scheduling deadline
Contact during regular business hours to schedule.
Inspection hours
Monday through Thursday, 7:30 AM to 4:00 PM (closed Fridays)

Typical sequence: Required inspections must be completed before proceeding to next construction phase. Final inspection required; structure may not be occupied until final sign-off.

Source: Public Works — Building and Development Division ↗

§ 06

Frequently asked

Common questions about Raymond permits

01 Do I need a building permit in Raymond, WA?
A building permit is required for all construction projects within the City of Raymond.
02 How much does a building permit cost in Raymond, WA?
Building permit fees in Raymond, WA are set by the local building department and vary by project type and valuation. Fees are calculated as: Set by City resolution; contact Tia Channell (360-942-4122) or tchannell@cityofraymond.com for current fee schedule..
03 How do I apply for a building permit in Raymond, WA?
To apply for a building permit in Raymond, WA, follow these steps: 1. Download the Building Packet or appropriate application form from the city website Forms page. 2. Complete the application with all required supporting documents (site plan, construction drawings). 3. Submit application to Tia Channell via email (tchannell@cityofraymond.com) or in person at City Hall. 4. Pay applicable fees in person or via InvoiceCloud online portal at time of submittal. 5. Building Inspector schedules review of submitted materials. 6. Schedule required inspections through Tia Channell during business hours (Monday–Thursday, 7:30 AM–4:00 PM). 7. Complete all required inspections before proceeding to next phase. 8. Receive final approval; structure may not be occupied until final inspection sign-off.
04 How long does it take to get a building permit in Raymond, WA?
Building permit processing times in Raymond, WA typically run Timeframe varies; direct contact with Building Permit Tech required for current schedule.. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Raymond, WA?
Not all construction work requires a permit in Raymond, WA. The following work is generally exempt: Fences 6 feet or shorter in height; Sheds and outbuildings 10 feet by 12 feet or smaller, with no permanent foundation, plumbing, or electrical connections; Residential re-roofing; Woodstove or heat pump installations (Mechanical Permit required). Note: Commercial re-roofing or roofing affecting the structural integrity of a building requires a permit. Confirm edge cases with the Building and Development Division before proceeding. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Raymond, WA?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Raymond, WA via: Tia Channell, Building Permit Tech: (360) 942-4122, tchannell@cityofraymond.com. Contact during regular business hours to schedule..
last verified April 2026 source Public Works — Building and Development Division ↗ entry id permits/washington/pacific/raymond

Educational reference. Permit rules and fees change — confirm current requirements directly with Public Works — Building and Development Division before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Pacific County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Pacific County jurisdictions →