§ 01

Permit authority

City of Woodland Community Development Department - Building Division

Street address
100 Davidson Avenue, Woodland, WA 98674
Coverage
All properties within the incorporated City of Woodland (spans both Cowlitz and Clark counties under unified municipal code).
Online portal
CloudPermit Online System
CloudPermit
§ 02

When a permit is required

Permit triggers and exempt work for Woodland

Building permits are required for all construction, alterations, and demolition within the City of Woodland.

Note: Building permits are required for ALL construction work including alteration, repairs, and demolition. Contact City of Woodland Building Division to confirm specific exemptions. Generally, minor repairs and maintenance, painting, papering, and similar finish work, and portable equipment not requiring permanent connection may be exempt.

Required documents
  • Completed online permit application
  • Site plan (for structures over 4,000 sq ft, Environmental Checklist required)
  • Construction plans and specifications
  • Proof of contractor registration with Washington State L&I
  • As-built drawings in AutoCAD .dwg format upon completion
Building code
International Building Code (IBC) with Washington amendments; International Residential Code (IRC); International Mechanical Code (IMC); Uniform Plumbing Code (UPC); Washington State Energy Code
Permit validity
Contact City for permit validity period.
Contractor requirements
All contractors must be registered with Washington State L&I and comply with City of Woodland requirements.

Source: City of Woodland Community Development Department - Building Division ↗

§ 03

Application process

Typical processing: Varies by project complexity. Contact Building Division for current timeframes.

  1. 01
    Sign up for a CloudPermit account and access the online portal.
  2. 02
    Complete the online permit application form for your project type.
  3. 03
    Prepare and upload required documentation: site plan, construction plans and specifications, proof of contractor registration with Washington State L&I.
  4. 04
    For structures over 4,000 sq ft, submit Environmental Checklist.
  5. 05
    Pay plan review fee at time of submittal (65% of building permit fee).
  6. 06
    Submit application through CloudPermit system.
  7. 07
    Development projects must go through site plan review (WMC 19.10). Site plan and engineering plans must be approved before utility extension.
  8. 08
    Pre-construction meeting required 48 hours before work begins.
  9. 09
    Pay remaining permit fees upon approval.
  10. 10
    Upon completion, submit as-built drawings in AutoCAD .dwg format.

Typical processing time: Varies by project complexity. Contact Building Division for current timeframes.

Source: City of Woodland Community Development Department - Building Division ↗

§ 04

Fee schedule

Effective 2019 (Resolution 715)

Fee type
Amount
01
Minimum permit fee
$27.03
02
Plan check fee
65% of building permit fee (paid at time of permit submittal)
03
Permit fee formula
Graduated valuation-based fee schedule. Examples: $1-$500 = $27.03; $501-$2,000 = $27.03 for first $500 + $3.51 per additional $100; $2,001-$25,000 = $79.64 for first $2,000 + $16.10 per additional $1,000; continuing through $1,000,001+ = $6,450.06 for first $1,000,000 + $4.20 per additional $1,000
04
Reinspection fee
$66 for plumbing; actual cost for mechanical and building

Contact City for payment methods. Impact fees: Single Family $5,900/unit; Multi-Family $5,900/unit; Accessory Dwelling Units $2,000/unit. Miscellaneous fees: Flood Development Permit $100; Fence (3'+) $55; Building Demolition $55; Residential Re-roof $55; Commercial Re-roof $100; Solid Fuel Burning Appliance $55; Commercial Coach Placement $250; Manufactured Home Installation (plan review without garage) $300; (with garage) $150. Plumbing: Permit issuance $40; Per fixture $10; Building sewer $19; Water heater $10; Backflow devices $15-$25. Mechanical: Permit issuance $35; Furnace installation $25-$30; Appliance vents $15; Repairs/alterations $25; Boilers $55-$75+. Sign: Window $75; Wall $100; Roof/projection $125; Free-standing $145; Monument $75.

§ 05

Required inspections

Scheduling and sequence

How to schedule
Scheduling deadline
48-hour notice required for pre-construction meeting before work begins

Typical sequence: Inspections required at various construction phases. Pre-construction meeting required 48 hours before work begins. Final inspection required for Certificate of Occupancy.

Source: City of Woodland Community Development Department - Building Division ↗

§ 06

Frequently asked

Common questions about Woodland permits

01 Do I need a building permit in Woodland, WA?
Building permits are required for all construction, alterations, and demolition within the City of Woodland.
02 How much does a building permit cost in Woodland, WA?
Building permit fees in Woodland, WA are set by the local building department and vary by project type and valuation. The minimum permit fee is $27.03. Fees are calculated as: Graduated valuation-based fee schedule. Examples: $1-$500 = $27.03; $501-$2,000 = $27.03 for first $500 + $3.51 per additional $100; $2,001-$25,000 = $79.64 for first $2,000 + $16.10 per additional $1,000; continuing through $1,000,001+ = $6,450.06 for first $1,000,000 + $4.20 per additional $1,000. Plan check fee: 65% of building permit fee (paid at time of permit submittal).
03 How do I apply for a building permit in Woodland, WA?
To apply for a building permit in Woodland, WA, follow these steps: 1. Sign up for a CloudPermit account and access the online portal. 2. Complete the online permit application form for your project type. 3. Prepare and upload required documentation: site plan, construction plans and specifications, proof of contractor registration with Washington State L&I. 4. For structures over 4,000 sq ft, submit Environmental Checklist. 5. Pay plan review fee at time of submittal (65% of building permit fee). 6. Submit application through CloudPermit system. 7. Development projects must go through site plan review (WMC 19.10). Site plan and engineering plans must be approved before utility extension. 8. Pre-construction meeting required 48 hours before work begins. 9. Pay remaining permit fees upon approval. 10. Upon completion, submit as-built drawings in AutoCAD .dwg format.
04 How long does it take to get a building permit in Woodland, WA?
Building permit processing times in Woodland, WA typically run Varies by project complexity. Contact Building Division for current timeframes.. Timelines can vary based on project complexity and current department workload.
05 How do I schedule a building inspection in Woodland, WA?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Woodland, WA via: CloudPermit System. 48-hour notice required for pre-construction meeting before work begins.
last verified April 2026 source City of Woodland Community Development Department - Building Division ↗ entry id permits/washington/cowlitz/woodland

Educational reference. Permit rules and fees change — confirm current requirements directly with City of Woodland Community Development Department - Building Division before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Cowlitz County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Cowlitz County jurisdictions →