Town of Richmond

How to apply for a building permit in Town of Richmond, Vermont. Permit authority, application steps, fees, and inspection requirements.

Min. permit fee
$50
Last verified
April 2026
On this page 6
§ 01

Permit authority

Planning and Zoning Office

Street address
203 Bridge Street, Richmond, VT 05477
Coverage
Richmond is a town on the Winooski River. The town enforces its own Zoning Regulations (effective August 25, 2025) and Building Energy Standards. Note: THE TOWN OF RICHMOND DOES NOT ISSUE ZONING COMPLIANCE CERTIFICATES.
§ 02

When a permit is required

Permit triggers and exempt work for Richmond

Zoning permit required for construction, structural alterations, additions, land development, and changes of use. ANR Atlas Map required with each zoning permit submission.

Note: Not publicly listed in accessible pages. Contact the Zoning Administrative Officer at 802-434-2430 for exempt work categories under Richmond Zoning Regulations.

Required documents
  • Zoning Permit application
  • ANR Atlas Map
  • Site plan
  • Drawings
  • Applicable checklists for DRB review types
Building code
Zoning Regulations (effective August 25, 2025); Vermont Building Energy Standards (residential and commercial); Vermont state building codes
Permit validity
Not specified on public pages; contact department.
Owner-builder
Not specified; contact department.
Contractor requirements
Vermont state licenses required for electrical, plumbing, and mechanical trades.
§ 03

Application process

Typical processing: Up to 30 days per state law; DRB projects require public hearing and have longer timelines.

  1. 01
    Contact the Zoning Administrative Officer at 802-434-2430 or ddenault@richmondvt.gov to discuss your project and confirm permit requirements.
  2. 02
    For all applications going before the Development Review Board, a pre-application meeting with staff is required; call to set up an appointment.
  3. 03
    Obtain the applicable application from the Planning and Zoning Office or from the town website.
  4. 04
    Prepare required documents: Zoning permit application; ANR Atlas Map (required with each zoning permit); site plan; drawings; applicable DRB checklists.
  5. 05
    Submit application with fee payment.
  6. 06
    Await processing; fee is calculated as total square feet x $0.40, minimum $50.
  7. 07
    Note: Richmond does NOT issue Zoning Compliance Certificates.

Typical processing time: Up to 30 days per state law; DRB projects require public hearing and have longer timelines.

Source: Planning and Zoning Office ↗

§ 04

Fee schedule

Effective July 2021

Fee type
Amount
01
Minimum permit fee
$50
02
Permit fee formula
Total square feet x $0.40, with a $50 minimum

Contact department for payment methods.

Fees change periodically. Confirm at the official fee schedule ↗ (effective July 2021) before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • 802-434-2430 (phone)
Inspection hours
Monday-Wednesday and Friday 8:00 AM - 4:00 PM; Thursday 10:00 AM - 4:00 PM. Remote appointments available; call ahead.

Typical sequence: Certificate of Occupancy issued upon completion. Note: Richmond does not issue Zoning Compliance Certificates.

§ 06

Frequently asked

Common questions about Richmond permits

01 Do I need a building permit in Richmond, VT?
Zoning permit required for construction, structural alterations, additions, land development, and changes of use. ANR Atlas Map required with each zoning permit submission.
02 How much does a building permit cost in Richmond, VT?
Building permit fees in Richmond, VT are set by the local building department and vary by project type and valuation. The minimum permit fee is $50. Fees are calculated as: Total square feet x $0.40, with a $50 minimum.
03 How do I apply for a building permit in Richmond, VT?
To apply for a building permit in Richmond, VT, follow these steps: 1. Contact the Zoning Administrative Officer at 802-434-2430 or ddenault@richmondvt.gov to discuss your project and confirm permit requirements. 2. For all applications going before the Development Review Board, a pre-application meeting with staff is required; call to set up an appointment. 3. Obtain the applicable application from the Planning and Zoning Office or from the town website. 4. Prepare required documents: Zoning permit application; ANR Atlas Map (required with each zoning permit); site plan; drawings; applicable DRB checklists. 5. Submit application with fee payment. 6. Await processing; fee is calculated as total square feet x $0.40, minimum $50. 7. Note: Richmond does NOT issue Zoning Compliance Certificates.
04 How long does it take to get a building permit in Richmond, VT?
Building permit processing times in Richmond, VT typically run Up to 30 days per state law; DRB projects require public hearing and have longer timelines.. Timelines can vary based on project complexity and current department workload.
05 How do I schedule a building inspection in Richmond, VT?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Richmond, VT via: 802-434-2430.
last verified April 2026 source Planning and Zoning Office ↗ entry id permits/vermont/chittenden/richmond

Educational reference. Permit rules and fees change — confirm current requirements directly with Planning and Zoning Office before applying. Jaspector is not legal advice.