Unincorporated Reeves County

How to apply for a building permit in unincorporated Reeves County, Texas. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

Reeves County Road and Bridge Permits Department

Street address
Road and Bridge administrative office: 31 County Road 201, P.O. Box 111, Pecos, TX 79772. Original mailed applications (effective January 1, 2026): Reeves County Treasurer's Office (Permits), 1714 Schmidt Drive, Pecos, TX 79772
Coverage
Unincorporated Reeves County only. The county provides permit and development controls for specific categories: on-site sewage, county road access and utility facilities in county rights-of-way, subdivision regulation, manufactured home rental community regulation, and food operation permits. No general countywide building permit for ordinary vertical construction is clearly documented.
Online portal
Reeves County iWorQ Portal
iWorQ
§ 02

When a permit is required

Permit triggers and exempt work for Reeves County

A general countywide building permit requirement for ordinary residential or commercial vertical construction in unincorporated Reeves County is not clearly documented. Verified county permit and development controls apply for: on-site sewage facilities, driveways and culverts in county right-of-way, utility facilities within county right-of-way, subdivision platting and development review, food operation permits, and manufactured home rental community regulation.

Note: No public countywide exempt-work list was found for a general building-permit program because no such program is clearly documented. Subdivision regulations include certain statutory exceptions to platting but these are not the same as a county building-permit exempt-work list.

Required documents
  • Varies by permit type. OSSF requires site evaluation, planning materials, directions, and legal-description support. Subdivision filings require plats, utility certifications, 911 addressing approval, tax documentation, roadway and drainage materials, and other checklist items.
Building code
No countywide adopted building code page for a general unincorporated building-permit program was found. Reeves County enforces subdivision regulations and OSSF requirements, and its subdivision materials reference county authority under Texas statutes for setbacks and related development controls.
Permit validity
OSSF Authorization to Construct is valid for 1 year from date of issuance. Subdivision regulations discuss development authorization expiration concepts but a simple countywide general permit expiration rule was not found.
Owner-builder
No countywide owner-builder rule was found. No public Reeves County implementation page for Texas HB 2833 private residential inspections was found.
Contractor requirements
OSSF work requires licensed site evaluators, designers, and installers. No general county contractor registration program for ordinary building construction was found.
§ 03

Application process

Typical processing: General permits: 1 to 2 weeks. OSSF final notice after successful inspection: within 7 calendar days.

  1. 01
    Confirm the parcel is in unincorporated Reeves County and identify which county control applies. Do not assume a general county building permit exists for ordinary construction.
  2. 02
    Use the county permits page and iWorQ portal to identify the applicable permit or regulation category: OSSF, driveway or culvert access, utility facilities within county right-of-way, subdivision, food operation, or manufactured home rental community requirements.
  3. 03
    Prepare the permit-specific application and supporting materials. For example, OSSF requires a site evaluation, planning materials, accurate directions, and legal-description support; subdivision applications require plats, utility approvals, 911 addressing, tax certificates, and other checklist items.
  4. 04
    Submit through the county's process. As of January 1, 2026, original applications must be mailed to the Treasurer's Office permits address as directed by the county notice.
  5. 05
    Pay the applicable fee through the Treasurer's Office. The county processes permits within 1 to 2 weeks.
  6. 06
    Complete any required permit-specific inspection. For OSSF, contact the office at least 5 working days in advance.
  7. 07
    Obtain the final county approval document. For OSSF, the county issues an Authorization to Construct first and then a Notice of Approval after successful inspection.

Typical processing time: General permits: 1 to 2 weeks. OSSF final notice after successful inspection: within 7 calendar days.

Source: Reeves County Road and Bridge Permits Department ↗

§ 04

Fee schedule

Reeves County building permit fees

Fee type
Amount
01
Minimum permit fee
OSSF single-family residential: $210.00. OSSF modification review: $110.00. Subdivision plat filing (recording fee): $120.00.
02
Plan check fee
OSSF modification review: $110.00 for single-family context; $210.00 for all other system types.
03
Permit fee formula
OSSF uses flat fees. Other county fees appear permit-specific rather than valuation-based.
04
Reinspection fee
OSSF: $100.00 for single-family residential systems; $200.00 for all other system types.

Payments should be made through the Treasurer's Office. The county accepts credit cards over the phone and in the office. OSSF applications state fees are non-refundable and must be paid by personal check, cashier's check, or money order. No cash accepted for OSSF.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • Contact Reeves County office at least 5 working days in advance (OSSF inspections) (phone)
Scheduling deadline
At least 5 working days in advance for OSSF inspections
Inspection hours
Monday-Thursday: 7:00 AM-6:00 PM. Some sources indicate 7:30 AM-6:00 PM.

Typical sequence: Varies by permit type. OSSF sequence: application review, Authorization to Construct, installation inspection before cover, then Notice of Approval. Subdivision sequence: checklist review, hearing process, and county approval actions rather than typical building-stage inspections.

Source: Reeves County Road and Bridge Permits Department ↗

§ 06

Frequently asked

Common questions about unincorporated Reeves County permits

01 Do I need a building permit in unincorporated Reeves County, TX?
A general countywide building permit requirement for ordinary residential or commercial vertical construction in unincorporated Reeves County is not clearly documented. Verified county permit and development controls apply for: on-site sewage facilities, driveways and culverts in county right-of-way, utility facilities within county right-of-way, subdivision platting and development review, food operation permits, and manufactured home rental community regulation.
02 How much does a building permit cost in unincorporated Reeves County, TX?
Building permit fees in unincorporated Reeves County, TX are set by the local building department and vary by project type and valuation. The minimum permit fee is OSSF single-family residential: $210.00. OSSF modification review: $110.00. Subdivision plat filing (recording fee): $120.00.. Fees are calculated as: OSSF uses flat fees. Other county fees appear permit-specific rather than valuation-based.. Plan check fee: OSSF modification review: $110.00 for single-family context; $210.00 for all other system types..
03 How do I apply for a building permit in unincorporated Reeves County, TX?
To apply for a building permit in unincorporated Reeves County, TX, follow these steps: 1. Confirm the parcel is in unincorporated Reeves County and identify which county control applies. Do not assume a general county building permit exists for ordinary construction. 2. Use the county permits page and iWorQ portal to identify the applicable permit or regulation category: OSSF, driveway or culvert access, utility facilities within county right-of-way, subdivision, food operation, or manufactured home rental community requirements. 3. Prepare the permit-specific application and supporting materials. For example, OSSF requires a site evaluation, planning materials, accurate directions, and legal-description support; subdivision applications require plats, utility approvals, 911 addressing, tax certificates, and other checklist items. 4. Submit through the county's process. As of January 1, 2026, original applications must be mailed to the Treasurer's Office permits address as directed by the county notice. 5. Pay the applicable fee through the Treasurer's Office. The county processes permits within 1 to 2 weeks. 6. Complete any required permit-specific inspection. For OSSF, contact the office at least 5 working days in advance. 7. Obtain the final county approval document. For OSSF, the county issues an Authorization to Construct first and then a Notice of Approval after successful inspection.
04 How long does it take to get a building permit in unincorporated Reeves County, TX?
Building permit processing times in unincorporated Reeves County, TX typically run General permits: 1 to 2 weeks. OSSF final notice after successful inspection: within 7 calendar days.. Timelines can vary based on project complexity and current department workload.
05 How do I schedule a building inspection in unincorporated Reeves County, TX?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in unincorporated Reeves County, TX via: Contact Reeves County office at least 5 working days in advance (OSSF inspections). At least 5 working days in advance for OSSF inspections.
last verified April 2026 source Reeves County Road and Bridge Permits Department ↗ entry id permits/texas/reeves/unincorporated