When a permit is required
Permit triggers and exempt work for Port Aransas
Building permits are required for covered construction work within the City of Port Aransas, including residential new construction, additions, and related work.
Note: Exempt work categories not specified in reviewed materials. Confirm with Building Department before proceeding with any work assumed exempt.
- Completed permit application
- Construction plans
- Site plan
- Drainage information
- Floodplain documentation
- Utility district materials
- Energy-compliance materials
- Contractor information
- Additional supporting documentation as required
- Building code
- City adopted 2018 ICC Codes, 2020 National Electrical Code, FEMA coastal requirements, Texas windstorm laws, and City of Port Aransas city code.
- Permit validity
- Permit validity period not specified in reviewed materials; confirm with Building Department.
- Owner-builder
- Owner-builder requirements should be confirmed with the Building Department.
- Contractor requirements
- Contractor information is required before permit issuance.
Source: Planning & Development; Building Department & Code Enforcement ↗
Application process
Typical processing: Processing timeframe not specified in reviewed materials; contact Building Department for current timeline.
- 01 Obtain a residential new-construction/addition permit packet from the City Building Department.
- 02 Review the packet requirements and gather required documentation including site plans, drainage information, floodplain items, utility district materials, and energy-compliance materials.
- 03 Provide contractor information before permit issuance.
- 04 Submit the completed application packet to the Building Department in person or by mail.
- 05 City staff reviews the application for completeness. Incomplete applications will not be accepted.
- 06 Provide all necessary supporting documentation before plan review begins.
- 07 Upon completeness review and approval, permit is issued.
- 08 Schedule inspections at required stages: footing/foundation, frame, final.
- 09 Obtain finished-floor elevation certificate, windstorm documentation, and energy-compliance certificate before certificate of occupancy issuance.
- 10 Receive certificate of occupancy upon final approval.
Typical processing time: Processing timeframe not specified in reviewed materials; contact Building Department for current timeline.
Source: Planning & Development; Building Department & Code Enforcement ↗
Fee schedule
Port Aransas building permit fees
Payment methods should be confirmed with Building Department.
Required inspections
Scheduling and sequence
- 361-749-4111 (phone)
- dpratt@cityofportaransas.org (email)
Typical sequence: Typical inspection sequence includes footing/foundation, frame, and final inspections. Additional inspections may be required based on project scope.
Policy on remote inspections not specified in reviewed materials.
Source: Planning & Development; Building Department & Code Enforcement ↗
Frequently asked
Common questions about Port Aransas permits
01 Do I need a building permit in Port Aransas, TX? ▸
02 How much does a building permit cost in Port Aransas, TX? ▸
03 How do I apply for a building permit in Port Aransas, TX? ▸
04 How long does it take to get a building permit in Port Aransas, TX? ▸
05 How do I schedule a building inspection in Port Aransas, TX? ▸