When a permit is required
Permit triggers and exempt work for Normangee
No HUD-code manufactured home may be located in the city without first obtaining a permit for use of a manufactured home as a dwelling. Mobile homes are prohibited, except lawful existing mobile homes already in place before the ordinance.
Note: No public general exempt-work list was found. The ordinance is project-specific to manufactured homes.
- Manufactured-home permit application
- Name, phone number, and residence address of applicant
- Exact location and legal description of the site
- Year, serial number, make, and size of the HUD-code manufactured home
- Photographs of the inside and outside of the home
- Application fee
- Building code
- Manufactured-home ordinance requires compliance with HUD and Texas Department of Housing and Community Affairs standards for manufactured housing.
Application process
Typical processing: Manufactured-home permit applications: within five business days of receipt by the City Secretary
- 01 Verify that the parcel is inside the Normangee city limits and specifically in the Leon County portion if the tract is near the county line.
- 02 Determine whether the project is the placement of a HUD-code manufactured home or another project for which direct city confirmation is needed.
- 03 For a manufactured home, obtain the city's Application for Permit for Use of a Manufactured Home as a Dwelling.
- 04 Complete all fields on the application, including applicant information, exact location and legal description, year model, serial number, make, and size.
- 05 Submit the application, the $25.00 application fee, and photographs of the inside and outside of the manufactured home to the city.
- 06 Wait for city review. The permit form says applications will be approved or denied within five business days of receipt by the City Secretary.
- 07 If approved, obtain the permit before locating the manufactured home and comply with the city's site, skirting, tie-down, and utility-connection requirements.
- 08 If the parcel is in a flood hazard area, also coordinate with the city floodplain administrator before development begins.
Typical processing time: Manufactured-home permit applications: within five business days of receipt by the City Secretary
Source: City of Normangee, Texas ↗
Fee schedule
Normangee building permit fees
Ordinance states the application fee is submitted with the application; ordinance text says fee by check or money order.
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- City review is built into the manufactured-home permit process (in-person)
Typical sequence: Typical sequence: site approval by a city representative, review by the mayor, permit issuance by the City Secretary, utility connection allowed only after meeting skirting and tie-down requirements.
Frequently asked
Common questions about Normangee permits
01 Do I need a building permit in Normangee, TX? ▸
02 How much does a building permit cost in Normangee, TX? ▸
03 How do I apply for a building permit in Normangee, TX? ▸
04 How long does it take to get a building permit in Normangee, TX? ▸
05 How do I schedule a building inspection in Normangee, TX? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with City of Normangee, Texas before applying. Jaspector is not legal advice.