On this page 5
When a permit is required
Permit triggers and exempt work for Talty
Building permits required for construction within the Town of Talty.
- Completed permit application
- Plot survey
- Site plan
- Construction plans
- Check for permit fees
- Contractor requirements
- All contractors must register before working in town. Registration cost is $100 per year for those not exempted.
Application process
Typical processing: Timeframe varies by project type and complexity.
- 01 Download building permit application from the town website under Development and Builder Essentials.
- 02 Prepare required documents including site plan, plot survey, and construction plans.
- 03 Submit permit application with check, plans, and plot survey to the town office.
- 04 Town staff reviews application for completeness and compliance.
- 05 Respond to any corrections or comments if required.
- 06 Obtain permit approval and schedule inspection by calling 972-552-9592.
- 07 Building Inspector Jeff Bagby will schedule and perform inspections.
Typical processing time: Timeframe varies by project type and complexity.
Required inspections
Scheduling and sequence
- 972-552-9592 (phone)
- Scheduling deadline
- Call the office before noon the previous day or after hours the day before or early the morning of inspection.
Typical sequence: Building Inspector: Jeff Bagby
Frequently asked
Common questions about Talty permits
01 Do I need a building permit in Talty, TX? ▸
02 How do I apply for a building permit in Talty, TX? ▸
03 How long does it take to get a building permit in Talty, TX? ▸
04 How do I schedule a building inspection in Talty, TX? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Town of Talty Development Services before applying. Jaspector is not legal advice.