On this page 6
When a permit is required
Permit triggers and exempt work for Wallis
The city requires building permits and instructs applicants to contact City Hall before starting a project. The city publishes forms for residential, commercial, utility, fire system, culvert, rental, and certificate of occupancy matters. Fence permits are required for fences 7 feet and over. A certificate of occupancy inspection is required whenever there is a change of use and/or ownership of an existing commercial building.
- Exempt Fences below 7 feet are not in the listed permit category (fence permits are required for fences 7 feet and over)
Note: Public permit page expressly states permits are required for fences 7 feet and over. No broader public exempt-work list was found.
- Varies by permit form
- Separate forms for new residential, residential remodel/addition, commercial permits, contractor registration, fire systems, culverts, rentals, and certificate of occupancy
- Building code
- Ordinance No. 221 adopts 2015 IBC, 2015 IRC, 2015 IFC, 2015 IECC, 2015 IFGC, 2015 IMC, 2015 IPC, 2015 IPMC, and 2014 NEC, with local amendments.
- Contractor requirements
- Contractors must register with the city. The registration fee is $100.00 and is good for one year.
Application process
Typical processing: Plan reviews can take a minimum of 5 days for residential and a minimum of 10 days for commercial.
- 01 Contact City Hall before starting the project.
- 02 Download the required permit form from the city permit page and complete contractor registration if applicable.
- 03 Submit the application for third-party plan review and city processing.
- 04 Allow for plan review timing published by the city.
- 05 Pay permit and registration fees.
- 06 Complete required third-party inspections and obtain any needed certificate of occupancy.
Typical processing time: Plan reviews can take a minimum of 5 days for residential and a minimum of 10 days for commercial.
Source: City of Wallis / City Hall ↗
Fee schedule
Wallis building permit fees
Contractor registration fee is $100.00 for one year. Other permit fees depend on the form and project type.
Required inspections
Scheduling and sequence
- City Hall (phone)
Typical sequence: The city states a third party performs all plan reviews and inspections. Application, third-party plan review, permit issuance, required inspections, and certificate of occupancy where applicable.
Source: City of Wallis / City Hall ↗
Frequently asked
Common questions about Wallis permits
01 Do I need a building permit in Wallis, TX? ▸
02 How do I apply for a building permit in Wallis, TX? ▸
03 How long does it take to get a building permit in Wallis, TX? ▸
04 What work is exempt from building permits in Wallis, TX? ▸
05 How do I schedule a building inspection in Wallis, TX? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with City of Wallis / City Hall before applying. Jaspector is not legal advice.