jaspector
City building permits

City of Pierre

How to apply for a building permit in City of Pierre, South Dakota. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

Pierre Building Department

Street address
2301 Patron Parkway, Pierre, SD 57501
Coverage
All projects within City of Pierre limits and its extra-territorial boundaries.
Online portal
City of Pierre OpenGov Portal
OpenGov
Additional resources
§ 02

When a permit is required

Permit triggers and exempt work for Pierre

Most projects require permits unless they fall within specific exemptions. Projects that DO require permits include most residential, commercial, and structural work.

Decks not more than 30 inches above adjacent grade without railings
Storage structures under 120 square feet
Painting, papering, tiling, carpeting, cabinets, counter tops
Platforms and sidewalks not exceeding 30 inches in height
Shallow swimming pools (under 24 inches deep, under 5,000 gallons)
Retaining walls less than 4 feet in height
Window awnings and playground equipment
  • Exempt Decks not more than 30 inches above adjacent grade without railings
  • Exempt Storage structures under 120 square feet
  • Exempt Painting, papering, tiling, carpeting, cabinets, counter tops
  • Exempt Platforms and sidewalks not exceeding 30 inches in height
  • Exempt Shallow swimming pools (under 24 inches deep, under 5,000 gallons)
  • Exempt Retaining walls less than 4 feet in height
  • Exempt Window awnings and playground equipment

Note: All projects not listed in the exemptions above require a building permit.

Required documents
  • Completed permit application
  • Associated project documents as specified on application
Building code
City of Pierre adopts the 2021 International Building Code (IBC), 2021 International Mechanical Code for mechanical systems, and the Uniform Plumbing Code as adopted by South Dakota.
Permit validity
Not publicly stated; contact Building Department
Owner-builder
Homeowners may apply for permits for owner-occupied structures.
Contractor requirements
Residential contractors must be licensed in the City of Pierre. Contractors may apply with owner approval.

Source: Pierre Building Department ↗

§ 03

Application process

Typical processing: Small projects: 2-4 days; Larger, complex projects: 1-4 weeks

  1. 01
    Complete a building permit application (available online at pierresd.portal.opengov.com or at City Hall).
  2. 02
    Submit application and associated documents to the Building Official for review.
  3. 03
    Building Official reviews application for compliance with adopted building codes.
  4. 04
    Receive feedback and approval/denial decision.
  5. 05
    Pay permit fees.
  6. 06
    Obtain issued permit before starting construction.

Typical processing time: Small projects: 2-4 days; Larger, complex projects: 1-4 weeks

Source: Pierre Building Department ↗

§ 04

Fee schedule

Pierre building permit fees

Fee type
Amount
01
Permit fee formula
Pierre maintains a detailed fee schedule. Specific fees vary by project type and valuation.
02
Penalty (no permit)
Minimum fine: $50 OR double the permit cost (whichever is greater)

Contact the Building Department at (605) 773-3071 or access the fee schedule through the online portal at pierresd.portal.opengov.com for current rates.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • (605) 773-3071 (phone)
Scheduling deadline
Not publicly stated; contact department
Inspection hours
Not publicly detailed; contact department
Time windows
Not publicly detailed; contact department

Typical sequence: Not publicly detailed; contact department

Source: Pierre Building Department ↗

§ 06

Frequently asked

Common questions about Pierre permits

01 Do I need a building permit in Pierre, SD?
Most projects require permits unless they fall within specific exemptions. Projects that DO require permits include most residential, commercial, and structural work.
02 How much does a building permit cost in Pierre, SD?
Building permit fees in Pierre, SD are set by the local building department and vary by project type and valuation. Fees are calculated as: Pierre maintains a detailed fee schedule. Specific fees vary by project type and valuation..
03 How do I apply for a building permit in Pierre, SD?
To apply for a building permit in Pierre, SD, follow these steps: 1. Complete a building permit application (available online at pierresd.portal.opengov.com or at City Hall). 2. Submit application and associated documents to the Building Official for review. 3. Building Official reviews application for compliance with adopted building codes. 4. Receive feedback and approval/denial decision. 5. Pay permit fees. 6. Obtain issued permit before starting construction.
04 How long does it take to get a building permit in Pierre, SD?
Building permit processing times in Pierre, SD typically run Small projects: 2-4 days; Larger, complex projects: 1-4 weeks. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Pierre, SD?
Not all construction work requires a permit in Pierre, SD. The following work is generally exempt: Decks not more than 30 inches above adjacent grade without railings; Storage structures under 120 square feet; Painting, papering, tiling, carpeting, cabinets, counter tops; Platforms and sidewalks not exceeding 30 inches in height; Shallow swimming pools (under 24 inches deep, under 5,000 gallons); Retaining walls less than 4 feet in height; Window awnings and playground equipment. Note: All projects not listed in the exemptions above require a building permit. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Pierre, SD?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Pierre, SD via: (605) 773-3071. Not publicly stated; contact department.
last verified April 2026 source Pierre Building Department ↗ entry id permits/south-dakota/hughes/pierre

Educational reference. Permit rules and fees change — confirm current requirements directly with Pierre Building Department before applying. Jaspector is not legal advice.