§ 01

Permit authority

Development Services / Building Inspection, Town of Clover

Street address
116 Bethel Street, Clover, SC 29710
Coverage
Applies inside the Town of Clover municipal limits only.
Online portal
Evolve Public Portal
Evolve Public Portal
§ 02

When a permit is required

Permit triggers and exempt work for Clover

Town guidance states zoning permits are required for projects ranging from new buildings to fences, additions, storage buildings, pools, and all new businesses; building permits are issued for new construction, remodels, additions, and alterations.

Note: No consolidated public exemption list was located on the reviewed Clover permit pages. Because Clover requires zoning permits for a broad range of residential improvements, confirm even seemingly minor exterior work before proceeding without approval.

Required documents
  • Building permit application
  • Site plan
  • Design drawings
  • Zoning compliance materials where applicable
  • Contractor license number
  • Town business license number
  • Owner and applicant information
  • Additional plan-review documents by project type
Building code
2021 International Residential Code and the current National Electrical Code are in effect. Public code data is otherwise thin and should be confirmed for non-residential and trade editions.
Permit validity
No general permit expiration period was clearly stated in the reviewed public pages.
Owner-builder
The town posts an Owner/Builder Disclosure Statement in its permit document center.
Contractor requirements
Clover's building permit application requires South Carolina licensed contractors for specialty work and states all businesses, including subcontractors, earning revenue inside town limits must have a Clover business license.

Source: Development Services / Building Inspection, Town of Clover ↗

§ 03

Application process

Typical processing: Building permit application states to allow a minimum of 48 hours for residential review and approval; zoning verification requests state allow up to 5 business days following receipt of a complete request to process.

  1. 01
    Determine whether the project first needs a zoning compliance permit, a building permit, or both; the town states many building projects require zoning compliance review first.
  2. 02
    Create an Evolve account and apply online for the correct permit category, or use the posted building permit form and submit the package as directed by Development Services.
  3. 03
    Upload or provide the completed application, site plan, and design drawings; the town building permit form calls for 2 paper copies and 1 electronic PDF copy.
  4. 04
    Include contractor licensing and business-license information, and provide any other project-specific plan-review documents.
  5. 05
    Wait for town review, respond to corrections if needed, and pay the applicable zoning and building fees.
  6. 06
    After issuance, request periodic inspections by phone or through the Evolve portal and proceed through the published inspection sequence.

Typical processing time: Building permit application states to allow a minimum of 48 hours for residential review and approval; zoning verification requests state allow up to 5 business days following receipt of a complete request to process.

Source: Development Services / Building Inspection, Town of Clover ↗

§ 04

Fee schedule

Clover building permit fees

Fee type
Amount
01
Minimum permit fee
$35 for zoning compliance permits
02
Plan check fee
Not clearly stated in the reviewed public fee materials.
03
Permit fee formula
Zoning compliance permits have a flat stated fee; building permit fees are valuation-based according to the town's business guidance page and permit fee schedule.
04
Reinspection fee
Public renovation guidance warns concealment before inspection can create extra costs; detailed reinspection fee amounts were not clearly exposed in the reviewed public materials.

Online Evolve submission is available; public fee pages reviewed did not clearly state card-processing rules.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
Scheduling deadline
24 hours notice required before each inspection.

Typical sequence: Clover publishes residential inspection, commercial inspection, and residential renovation schedules; work may not proceed beyond each successive stage until approval is obtained, subject to limited simultaneous inspections.

Source: Development Services / Building Inspection, Town of Clover ↗

§ 06

Frequently asked

Common questions about Clover permits

01 Do I need a building permit in Clover, SC?
Town guidance states zoning permits are required for projects ranging from new buildings to fences, additions, storage buildings, pools, and all new businesses; building permits are issued for new construction, remodels, additions, and alterations.
02 How much does a building permit cost in Clover, SC?
Building permit fees in Clover, SC are set by the local building department and vary by project type and valuation. The minimum permit fee is $35 for zoning compliance permits. Fees are calculated as: Zoning compliance permits have a flat stated fee; building permit fees are valuation-based according to the town's business guidance page and permit fee schedule.. Plan check fee: Not clearly stated in the reviewed public fee materials..
03 How do I apply for a building permit in Clover, SC?
To apply for a building permit in Clover, SC, follow these steps: 1. Determine whether the project first needs a zoning compliance permit, a building permit, or both; the town states many building projects require zoning compliance review first. 2. Create an Evolve account and apply online for the correct permit category, or use the posted building permit form and submit the package as directed by Development Services. 3. Upload or provide the completed application, site plan, and design drawings; the town building permit form calls for 2 paper copies and 1 electronic PDF copy. 4. Include contractor licensing and business-license information, and provide any other project-specific plan-review documents. 5. Wait for town review, respond to corrections if needed, and pay the applicable zoning and building fees. 6. After issuance, request periodic inspections by phone or through the Evolve portal and proceed through the published inspection sequence.
04 How long does it take to get a building permit in Clover, SC?
Building permit processing times in Clover, SC typically run Building permit application states to allow a minimum of 48 hours for residential review and approval; zoning verification requests state allow up to 5 business days following receipt of a complete request to process.. Timelines can vary based on project complexity and current department workload.
05 How do I schedule a building inspection in Clover, SC?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Clover, SC via: Evolve portal, 803-222-9495. 24 hours notice required before each inspection..
last verified April 2026 source Development Services / Building Inspection, Town of Clover ↗ entry id permits/south-carolina/york/clover

Educational reference. Permit rules and fees change — confirm current requirements directly with Development Services / Building Inspection, Town of Clover before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in York County.

Same county, different permit office. Click for that jurisdiction's full guide.

All York County jurisdictions →