§ 01

Permit authority

Town of Edisto Beach, Building Department

Street address
2414 Murray Street, Edisto Beach, SC 29438
Coverage
All properties within the incorporated Town of Edisto Beach, including beachfront and coastal areas subject to special lighting and environmental restrictions.
Online portal
Town of Edisto Beach Forms and Applications
Town of Edisto Beach Portal
§ 02

When a permit is required

Permit triggers and exempt work for Edisto Beach

A building permit is required for construction/remodeling exceeding $2,000 within the Town of Edisto Beach. All projects in beachfront areas are subject to special lighting and environmental restrictions.

Required documents
  • All fields on the building permit form must be completed
  • Tree survey with building footprint
  • SCDHEC Permit to Construct for septic system OR paid sewer tap receipt
  • Property Owner Letter of Authorization OR signed builder/owner contract OR Owner/Builder Affidavit
  • Proof of ownership
  • Detailed construction drawings (site plan, floor plans, elevation drawings)
  • Electrical, plumbing, mechanical, and fire protection plans
  • Evidence of professional licensure (contractors) where required
  • Zoning Certificate (if applicable)
Building code
International Residential Building, Plumbing, Electrical, Mechanical, and Fire codes, plus 2021 International Swimming Pool and Spa Code, along with local Zoning, Subdivision, and Code of General Ordinances
Permit validity
Building permit is not valid until final inspection is completed and approved. Verify validity period with Building Department.
Contractor requirements
A Town business license is required of all contractors. Certain work (general construction, electrical, HVAC, plumbing) must be performed only by licensed individuals. South Carolina Contractor's License required for work exceeding $10,000.
§ 03

Application process

Typical processing: Varies based on application completeness and site visit scheduling. Contact Building Department at 843-869-2505 for estimated timeline.

  1. 01
    Obtain Zoning Certificate if required for any change in use, even without a building permit.
  2. 02
    Prepare complete application package: all fields on building permit form completed, tree survey with building footprint, SCDHEC Permit to Construct for septic system OR paid sewer tap receipt, Property Owner Letter of Authorization OR signed builder/owner contract OR Owner/Builder Affidavit, proof of ownership, detailed construction drawings (site plan, floor plans, elevation drawings), electrical, plumbing, mechanical, and fire protection plans, and evidence of professional licensure where required.
  3. 03
    Submit all complete documents by mail or hand-delivery to: 2414 Murray Street, Edisto Beach, SC 29438, or email to: Building@townofedistobeach.com.
  4. 04
    Schedule mandatory site visit with Building Official or designee to evaluate property suitability and construction feasibility. All documents must be complete before site visit can be scheduled.
  5. 05
    Building Official conducts site visit and reviews application for compliance.
  6. 06
    Permit is issued if site visit and application review are satisfactory.
  7. 07
    Construction proceeds with required inspections at code-specified stages.
  8. 08
    Obtain Final Inspection approval and Certificate of Occupancy. Building permit is not valid until final inspection is completed and approved.

Typical processing time: Varies based on application completeness and site visit scheduling. Contact Building Department at 843-869-2505 for estimated timeline.

Source: Town of Edisto Beach, Building Department ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • 843-869-2505 (phone)
  • Building@townofedistobeach.com (email)
Inspection hours
Monday-Friday, 8:00 AM-4:30 PM

Typical sequence: Multiple inspections required during construction at code-specified stages. Mandatory site visit by Building Official required before permit issuance. All documents must be complete before site visit can be scheduled.

Source: Town of Edisto Beach, Building Department ↗

§ 05

Frequently asked

Common questions about Edisto Beach permits

01 Do I need a building permit in Edisto Beach, SC?
A building permit is required for construction/remodeling exceeding $2,000 within the Town of Edisto Beach. All projects in beachfront areas are subject to special lighting and environmental restrictions.
02 How do I apply for a building permit in Edisto Beach, SC?
To apply for a building permit in Edisto Beach, SC, follow these steps: 1. Obtain Zoning Certificate if required for any change in use, even without a building permit. 2. Prepare complete application package: all fields on building permit form completed, tree survey with building footprint, SCDHEC Permit to Construct for septic system OR paid sewer tap receipt, Property Owner Letter of Authorization OR signed builder/owner contract OR Owner/Builder Affidavit, proof of ownership, detailed construction drawings (site plan, floor plans, elevation drawings), electrical, plumbing, mechanical, and fire protection plans, and evidence of professional licensure where required. 3. Submit all complete documents by mail or hand-delivery to: 2414 Murray Street, Edisto Beach, SC 29438, or email to: Building@townofedistobeach.com. 4. Schedule mandatory site visit with Building Official or designee to evaluate property suitability and construction feasibility. All documents must be complete before site visit can be scheduled. 5. Building Official conducts site visit and reviews application for compliance. 6. Permit is issued if site visit and application review are satisfactory. 7. Construction proceeds with required inspections at code-specified stages. 8. Obtain Final Inspection approval and Certificate of Occupancy. Building permit is not valid until final inspection is completed and approved.
03 How long does it take to get a building permit in Edisto Beach, SC?
Building permit processing times in Edisto Beach, SC typically run Varies based on application completeness and site visit scheduling. Contact Building Department at 843-869-2505 for estimated timeline.. Timelines can vary based on project complexity and current department workload.
04 How do I schedule a building inspection in Edisto Beach, SC?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Edisto Beach, SC via: 843-869-2505, Building@townofedistobeach.com.
last verified April 2026 source Town of Edisto Beach, Building Department ↗ entry id permits/south-carolina/colleton/edisto-beach

Educational reference. Permit rules and fees change — confirm current requirements directly with Town of Edisto Beach, Building Department before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Colleton County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Colleton County jurisdictions →