When a permit is required
Permit triggers and exempt work for Aiken County
A building permit is required for all construction in unincorporated Aiken County.
- Building permit application form
- Two (2) sets of drawings/plans
- Site plan showing structure location (for residential construction)
- Recorded plat, scaled drawing, or scaled aerial photo from Aiken County GeoServices (for residential construction)
- Building code
- 2021 International Building Code (IBC) with SC amendments, 2021 International Residential Code (IRC) with SC amendments, 2021 International Fire Code with SC amendments, ICC/ANSI A117.1 (mandatory)
- Contractor requirements
- SC general contractor, mechanical contractor, or residential builder license required (statewide requirement from SC LLR Contractor's Licensing Board). Two-year work experience in relevant classification required; must pass examination with 70% minimum score.
Application process
Typical processing: Varies by permit complexity; online status tracking available
- 01 Complete building permit application form (available on county website and CitizenServe portal)
- 02 Submit two (2) sets of drawings/plans with application
- 03 For residential construction, submit site plan showing structure location via recorded plat, scaled drawing on graph paper, or scaled aerial photo from Aiken County GeoServices
- 04 Submit through CitizenServe online portal or in person
- 05 Processing time: varies by permit complexity; county provides online status tracking
- 06 Permit is issued upon approval and fee payment
Typical processing time: Varies by permit complexity; online status tracking available
Fee schedule
Effective 2025-07-30
1.49% transaction fee added if paying by MasterCard, Visa, or Discover. Payment methods: credit card, cash, or check. Fees must be paid prior to permit issuance. Manufactured Home Development Permit: $15.00. Manufactured Home Moving Permit: $30.00.
Required inspections
Scheduling and sequence
- 803-642-1520 (phone)
- CitizenServe portal (online)
- Scheduling deadline
- Minimum one (1) working day advance notice; inspection requests must be called in before 5:00 pm to be scheduled for next business day
Frequently asked
Common questions about unincorporated Aiken County permits
01 Do I need a building permit in unincorporated Aiken County, SC? ▸
02 How much does a building permit cost in unincorporated Aiken County, SC? ▸
03 How do I apply for a building permit in unincorporated Aiken County, SC? ▸
04 How long does it take to get a building permit in unincorporated Aiken County, SC? ▸
05 How do I schedule a building inspection in unincorporated Aiken County, SC? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Aiken County Planning & Development Department before applying. Jaspector is not legal advice.