When a permit is required
Permit triggers and exempt work for Harmony Township
New construction and other regulated work require the shared county/municipal permit process, and any new impervious surface needs county stormwater review.
- Exempt Fences no more than 6 feet high
- Exempt Retaining walls no more than 4 feet unless supporting surcharge
- Exempt Certain water tanks on grade up to 5,000 gallons
- Exempt Sidewalks and driveways not over a basement
- Exempt Shallow prefabricated pools
- Exempt Playground equipment
- Exempt Some window awnings
- Exempt Low uncovered decks
- Exempt Communications wiring
Note: Harmony's local sewage, county stormwater, or other municipal controls may still apply even when UCC work is exempt.
- Shared Forest County permit application
- Sketch showing buildings and distances to property lines
- Sewage permit if applicable
- Highway permit if applicable
- Floodplain information if applicable
- Workers compensation documentation when applicable
- Cabin affidavit if applicable
- Building code
- Pennsylvania Uniform Construction Code; Harmony Township is OPT-IN with amendments.
- Permit validity
- State UCC 180-day start/inactivity rule and 5-year outer validity limit apply.
- Owner-builder
- No special Harmony owner-builder rule was posted beyond the shared workers compensation and recreational cabin affidavit forms.
- Contractor requirements
- HICPA registration applies for home improvement contractors over $5,000.
Application process
Typical processing: State UCC timelines are 15 business days for residential permits and 30 business days for commercial permits unless extended by agreement.
- 01 Contact Harmony Township or Derrick D. Beach to schedule an appointment and confirm what township, sewage, and county approvals apply.
- 02 Complete the posted Harmony Township building permit packet, which is the shared Forest County Municipal Permit/Prior Approval Application form.
- 03 Attach the required sketch, sewage or highway permits if applicable, and the UCC Recreational Cabin Affidavit if the project is a recreational cabin.
- 04 File the county stormwater portion and fee with Forest County Conservation District and Planning.
- 05 After county stormwater approval, Harmony Township completes the local building permit review and signs the permit.
- 06 Notify the issuing officer upon completion so required inspections can be closed out.
Typical processing time: State UCC timelines are 15 business days for residential permits and 30 business days for commercial permits unless extended by agreement.
Fee schedule
Harmony Township building permit fees
County materials require full fee payment before plan approval.
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- 814-463-7783 (phone)
- Inspection hours
- By appointment only
Typical sequence: Required inspections occur as directed by the code official before final closeout.
Frequently asked
Common questions about Harmony Township permits
01 Do I need a building permit in Harmony Township, PA? ▸
02 How much does a building permit cost in Harmony Township, PA? ▸
03 How do I apply for a building permit in Harmony Township, PA? ▸
04 How long does it take to get a building permit in Harmony Township, PA? ▸
05 What work is exempt from building permits in Harmony Township, PA? ▸
06 How do I schedule a building inspection in Harmony Township, PA? ▸