When a permit is required
Permit triggers and exempt work for Madras
City requires permits for structural changes, electrical work, plumbing, mechanical systems, and major renovations. City code provisions in Title 18 (Development Code) govern land use and development review.
- Exempt Work meeting Oregon residential exemption thresholds (small detached structures, low fences, retaining walls, finish work, etc.)
Note: City development code and zoning compliance may still apply even where building permit is exempt; applicants should verify with city before assuming work is exempt
- City-side materials vary by project type per city checklists
- Building application
- Site plan
- Construction plans
- Structural/MEP details
- Building code
- Oregon State Building Code as administered through city and county coordination
- Permit validity
- Standard Oregon 180-day permit expiration applies; permits expire if final inspection not conducted within 180 days of issuance
- Owner-builder
- Madras code pages do not publish separate owner-builder restrictions beyond Oregon law
- Contractor requirements
- Oregon CCB and specialty BCD licenses required for hired contractors performing regulated work
Application process
Application → plan check → issuance → inspection → final
- 01 Consult with City of Madras Community Development Department to confirm development criteria and zoning compliance prior to formal application
- 02 Consult with City of Madras Public Works Department for site development, utility, and access requirements
- 03 Prepare city-required application and supporting documents per city checklists; city provides enhanced structural, mechanical, electrical, and plumbing review (effective May 1, 2020)
- 04 Submit to City of Madras Community Development for local plan review and approval
- 05 Once City of Madras approves the project, submit the city-approved application and documents to Jefferson County Community Development Department
- 06 County processes the building permit application through Oregon ePermitting; county will not issue without city approval documented
- 07 Create Oregon ePermitting account if not already established, upload county-required documents
- 08 County reviews for completeness; pay fees when invoiced through ePermitting
- 09 After approval and fee payment, permit is issued and construction may begin; schedule required inspections
Fee schedule
Madras building permit fees
Both city and county fees must be paid; applicants should confirm fee structure with both jurisdictions
Required inspections
Scheduling and sequence
- Oregon ePermitting (online)
- (541) 475-2344 (phone)
- Inspection hours
- Monday-Friday 8:00 a.m. - 5:00 p.m.
Typical sequence: County inspection sequence applies; city may also require final site review before certificate of occupancy
Frequently asked
Common questions about Madras permits
01 Do I need a building permit in Madras, OR? ▸
02 How much does a building permit cost in Madras, OR? ▸
03 How do I apply for a building permit in Madras, OR? ▸
04 What work is exempt from building permits in Madras, OR? ▸
05 How do I schedule a building inspection in Madras, OR? ▸