City Building Permits

Brookings, OR - 2026 Building Permit Guide

How to apply for a building permit in Brookings, Oregon. Permit authority, application steps, fees, and inspection requirements.

Oregon Curry County Updated March 2026

Permit Authority

All properties within the incorporated City of Brookings.

Department
Curry County Building Division (administered jointly) / City of Brookings Planning & Development Services Department
Address
94235 Moore St., Suite 113, Gold Beach, OR 97444
Phone
(541) 247-3304 (Building Permits) / (541) 469-1135 (City Planning)

Online Permit Portal

Platform: Accela • Account required: Yes • Submission: Online only

Application Process

  1. Submit Building Permit Clearance Form to City of Brookings describing project and zoning compliance
  2. Prepare two complete sets of plans: site plan, floor plans, and cross-sections with construction details
  3. Submit application with required documentation to Curry County Building Division at the Moore St. office
  4. Provide property address, legal description, project description, owner/contractor information, and construction cost estimate
  5. Pay plan review fee upon application submission
  6. Plan review conducted concurrently with application
  7. Pay remaining permit fees upon approval
  8. Permit issued upon fee payment and plan approval

Typical processing time: Plan review concurrent with application; timeline varies based on project complexity

Source: Curry County Building Division (administered jointly) / City of Brookings Planning & Development Services Department

General Requirements

All new construction, structural renovations and alterations, and mechanical/plumbing/electrical changes require permits.

Required Documents

  • Building Permit Clearance Form from City of Brookings
  • Property address and legal description
  • Project description and scope of work
  • Owner name, address, phone, and email
  • Contractor name, address, phone, CCB license number (if applicable)
  • City business license (if applicable)
  • Construction cost estimate (used for fee calculation)
  • Two complete sets of construction plans
Building code
Oregon State Building Code, Brookings Planning Handbook, and Brookings Development Code (OAR Chapter 33)
Contractor requirements
All construction work for compensation requires a valid Oregon Construction Contractors Board (CCB) license with appropriate endorsement.

Fees

Permit fee formula
Based on project value (all construction costs including labor, materials, equipment, contractor profit)
Payment note
State surcharge: 12% of permit fee. Inspection fees included in permit schedule. Contact Curry County Building Division for current fee schedule.

Work That Does NOT Require a Permit

  • Simple outdoor sheds less than 200 sq ft and less than 10 ft height (with conditions)

Inspections

How to Schedule

  • (541) 247-3304 (Building Permits) / (541) 469-1135 (Building Official) (phone)
Scheduling deadline
24-hour advance notice required
Inspection hours
Monday–Friday, 9:00 AM – 4:00 PM

Typical inspection sequence: Compliance with Oregon specialty codes—structural, mechanical, plumbing, electrical

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Curry County Building Division (administered jointly) / City of Brookings Planning & Development Services Department before applying.

Frequently Asked Questions

Brookings Building Permit FAQ

Do I need a building permit in Brookings, OR?
All new construction, structural renovations and alterations, and mechanical/plumbing/electrical changes require permits.
How much does a building permit cost in Brookings, OR?
Fees are calculated as: Based on project value (all construction costs including labor, materials, equipment, contractor profit).
How do I apply for a building permit in Brookings, OR?
1. Submit Building Permit Clearance Form to City of Brookings describing project and zoning compliance 2. Prepare two complete sets of plans: site plan, floor plans, and cross-sections with construction details 3. Submit application with required documentation to Curry County Building Division at the Moore St. office 4. Provide property address, legal description, project description, owner/contractor information, and construction cost estimate 5. Pay plan review fee upon application submission 6. Plan review conducted concurrently with application 7. Pay remaining permit fees upon approval 8. Permit issued upon fee payment and plan approval
How long does it take to get a building permit in Brookings, OR?
Typical processing time is Plan review concurrent with application; timeline varies based on project complexity.
What work is exempt from building permits in Brookings, OR?
The following work is generally exempt: Simple outdoor sheds less than 200 sq ft and less than 10 ft height (with conditions).
How do I schedule a building inspection in Brookings, OR?
Inspections can be scheduled via: (541) 247-3304 (Building Permits) / (541) 469-1135 (Building Official). 24-hour advance notice required.

Need help with your project?

Navigating permits in Brookings can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.

Other cities in Curry County

View all Curry County jurisdictions →