When a permit is required
Permit triggers and exempt work for Pickaway County
Commercial instructions require sealed plans for commercial work; the county also requires all contractors to be registered with Pickaway County
- Four sets of plans or pdf files, site plan/plot plan, foundation plan, floor plan, elevation plan, electrical plan, mechanical plan, plumbing plan, sprinkler plan if required, energy and ADA compliance data
- Building code
- Ohio Building Code, which is based on IBC 2021 with Ohio amendments
- Contractor requirements
- All contractors must be registered with Pickaway County
Fee schedule
Pickaway County building permit fees
Required inspections
Scheduling and sequence
- Call in inspections by 2:00 pm for next-day inspections (phone)
Typical sequence: Structural inspections include footing/foundation, floor slab, framing, insulation, fire-resistant penetrations, and final. Mechanical includes under-slab, piping, rough-in, above ceiling, fire-resistant penetrations, kitchen exhaust hood, and final. Electrical includes temporary and new services, under-slab, rough-in, above ceiling, fire-resistant penetrations, and final. Plumbing includes underground, rough-in, above ceiling, and final
Frequently asked
Common questions about unincorporated Pickaway County permits
01 Do I need a building permit in unincorporated Pickaway County, OH? ▸
02 How do I schedule a building inspection in unincorporated Pickaway County, OH? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Pickaway County Building Department before applying. Jaspector is not legal advice.