§ 01

Permit authority

Stutsman County Tax Equalization and Zoning Department

Street address
511 2nd Ave SE Suite 102, Jamestown, ND 58401
Coverage
All unincorporated areas within Stutsman County, subject to township zoning oversight.
§ 02

When a permit is required

Permit triggers and exempt work for Stutsman County

Building permits required for most structural, mechanical, and utility work in unincorporated Stutsman County.

Minor cosmetic improvements; verify with county zoning office.
  • Exempt Minor cosmetic improvements; verify with county zoning office.

Note: Exempt from building permit does not mean exempt from zoning and subdivision plat requirements. All building in unincorporated areas must occur in Board-approved subdivisions per North Dakota Century Code.

Required documents
  • Completed Application For Permit form
  • Property description and legal description
  • Subdivision plat approval documentation from Board of County Commissioners
  • Project scope and construction plans
  • Proof of property ownership or authorization
Building code
North Dakota model building code (2024 IBC/IRC) applied selectively. Code adoption varies by township; verify local requirements before submittal.
Permit validity
Contact county office for permit validity period and renewal requirements.
Owner-builder
Owner-builders must comply with North Dakota building standards and provide required documentation.
Contractor requirements
Contractors must be licensed for specialty trades (electrical, plumbing) with state boards. General contractor licensing may be required depending on township.
§ 03

Application process

Typical processing: 2-4 weeks depending on subdivision plat approval status and complexity.

  1. 01
    Contact Stutsman County Tax Equalization office or township zoning officer for your area.
  2. 02
    Obtain the 'Application For Permit' form from county website or office.
  3. 03
    Complete application with property details and project scope.
  4. 04
    Submit application to Tax Equalization office or relevant township zoning officer.
  5. 05
    Ensure property is in an approved subdivision per North Dakota Century Code.
  6. 06
    County Board of Commissioners must approve subdivision plat before building permits can be issued.
  7. 07
    Once subdivision approval obtained, building permit may be issued upon fee payment.

Typical processing time: 2-4 weeks depending on subdivision plat approval status and complexity.

Source: Stutsman County Tax Equalization and Zoning Department ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • (701) 252-9032 (phone)
Inspection hours
Monday-Friday, 8 AM to 5 PM

Typical sequence: Stutsman County does not provide electrical, plumbing, or mechanical inspections. These must be coordinated with North Dakota State Boards.

§ 05

Frequently asked

Common questions about unincorporated Stutsman County permits

01 Do I need a building permit in unincorporated Stutsman County, ND?
Building permits required for most structural, mechanical, and utility work in unincorporated Stutsman County.
02 How do I apply for a building permit in unincorporated Stutsman County, ND?
To apply for a building permit in unincorporated Stutsman County, ND, follow these steps: 1. Contact Stutsman County Tax Equalization office or township zoning officer for your area. 2. Obtain the 'Application For Permit' form from county website or office. 3. Complete application with property details and project scope. 4. Submit application to Tax Equalization office or relevant township zoning officer. 5. Ensure property is in an approved subdivision per North Dakota Century Code. 6. County Board of Commissioners must approve subdivision plat before building permits can be issued. 7. Once subdivision approval obtained, building permit may be issued upon fee payment.
03 How long does it take to get a building permit in unincorporated Stutsman County, ND?
Building permit processing times in unincorporated Stutsman County, ND typically run 2-4 weeks depending on subdivision plat approval status and complexity.. Timelines can vary based on project complexity and current department workload.
04 What work is exempt from building permits in unincorporated Stutsman County, ND?
Not all construction work requires a permit in unincorporated Stutsman County, ND. The following work is generally exempt: Minor cosmetic improvements; verify with county zoning office.. Note: Exempt from building permit does not mean exempt from zoning and subdivision plat requirements. All building in unincorporated areas must occur in Board-approved subdivisions per North Dakota Century Code. When in doubt, confirm with the local building department before starting work.
05 How do I schedule a building inspection in unincorporated Stutsman County, ND?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in unincorporated Stutsman County, ND via: (701) 252-9032.
last verified April 2026 source Stutsman County Tax Equalization and Zoning Department ↗ entry id permits/north-dakota/stutsman/unincorporated