When a permit is required
Permit triggers and exempt work for Arnegard
A building permit is required for all new construction, additions, alterations, and changes of occupancy in Arnegard.
- Exempt Minor exemptions may exist for small accessory structures; confirm with Building Department
Note: All new construction is generally required to obtain a permit. Confirm exemption status with the McKenzie County Building Department before proceeding.
- Completed permit application packet
- Site plan and property survey
- Construction plans and specifications
- Project scope and cost estimate
- Proof of property ownership or authorization
- Building code
- North Dakota State Building Code (2024 version effective January 1, 2026), including International Building Code (IBC), International Residential Code (IRC), International Mechanical Code (IMC), International Fuel Gas Code (IFGC), and International Energy Conservation Code (IECC)
- Permit validity
- Permit validity period should be confirmed with the Building Department at (701) 444-2533.
- Owner-builder
- Owner-builders must provide appropriate documentation and meet all code compliance requirements.
- Contractor requirements
- Contractors must comply with North Dakota state licensing requirements. For jobs exceeding $4,000, a State of North Dakota contractor license is required.
Source: McKenzie County Building Department (Arnegard Administration) ↗
Application process
Typical processing: 10-15 business days
- 01 Download the appropriate permit application packet from the McKenzie County Building Department.
- 02 Complete all required application forms with project details and documentation.
- 03 Submit the completed packet via email to building@co.mckenzie.nd.us or through the online portal.
- 04 County staff reviews the application for completeness. Incomplete applications will not be accepted.
- 05 Upon receiving all required documents, the permit process takes approximately 10-15 business days.
- 06 Do not submit payment until staff review is complete.
- 07 Once approved, obtain the permit and pay all required fees.
- 08 Permit must be kept on-site at all times and available for inspection.
Typical processing time: 10-15 business days
Source: McKenzie County Building Department (Arnegard Administration) ↗
Fee schedule
Arnegard building permit fees
Fees are payable upon permit approval. Contact building@co.mckenzie.nd.us for the current fee schedule.
Required inspections
Scheduling and sequence
- building@co.mckenzie.nd.us (email)
- (701) 444-2533 (phone)
- Inspection hours
- Contact Building Department for office hours and inspection availability
Typical sequence: Mandatory inspections include: (1) Footings after dug/formed with rebar placed, (2) Foundation after forms set and rebar placed, (3) Framing after complete but before siding/insulation/MEP, (4) Sheetrock after nailed/screwed but before taping, (5) Final inspection before occupancy.
Source: McKenzie County Building Department (Arnegard Administration) ↗
Frequently asked
Common questions about Arnegard permits
01 Do I need a building permit in Arnegard, ND? ▸
02 How much does a building permit cost in Arnegard, ND? ▸
03 How do I apply for a building permit in Arnegard, ND? ▸
04 How long does it take to get a building permit in Arnegard, ND? ▸
05 What work is exempt from building permits in Arnegard, ND? ▸
06 How do I schedule a building inspection in Arnegard, ND? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with McKenzie County Building Department (Arnegard Administration) before applying. Jaspector is not legal advice.