§ 01

Permit authority

Town of Tyre Zoning Enforcement Officer

Street address
1082 Gravel Road, Seneca Falls, NY 13148
Coverage
All properties within the Town of Tyre.
Online portal
Zoning Enforcement
Town of Tyre
Additional resources
§ 02

When a permit is required

Permit triggers and exempt work for Tyre

A zoning permit is required before construction, alteration, or change of use that must comply with the Town of Tyre zoning law.

Note: Contact Zoning Enforcement Officer to verify exemption status. Seneca County may require a separate building permit.

Required documents
  • Zoning permit application
  • Site plan
  • Construction plans and specifications
Building code
New York State Uniform Building Code, New York State Energy Conservation Construction Code
Permit validity
Permit validity follows town policies; generally renewable.
Owner-builder
Owner-builders must comply with zoning permit requirements.
Contractor requirements
Contractors must be licensed and comply with state and local requirements.

Source: Town of Tyre Zoning Enforcement Officer ↗

§ 03

Application process

Typical processing: Generally 30 days for standard zoning permits; longer if special review required.

  1. 01
    Contact Zoning Enforcement Officer Reginald Aceto at (315) 835-0163 or zoningofficer@tyreny.gov.
  2. 02
    Obtain zoning permit application from Zoning Enforcement Officer.
  3. 03
    Complete application and prepare required site plan and construction documentation.
  4. 04
    Submit application to Zoning Enforcement Officer with fee.
  5. 05
    Zoning permits are generally issued within 30 days unless site-plan review, special-use approval, or variance is needed.
  6. 06
    Confirm with Seneca County Code Enforcement whether a county building permit is also required.

Typical processing time: Generally 30 days for standard zoning permits; longer if special review required.

Source: Town of Tyre Zoning Enforcement Officer ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • (315) 835-0163 (phone)
  • zoningofficer@tyreny.gov (email)
Scheduling deadline
Contact Zoning Enforcement for scheduling requirements.
Inspection hours
Contact town for office hours.

Typical sequence: Town zoning inspections; county may conduct building or fire code inspections if required.

Source: Town of Tyre Zoning Enforcement Officer ↗

§ 05

Frequently asked

Common questions about Tyre permits

01 Do I need a building permit in Tyre, NY?
A zoning permit is required before construction, alteration, or change of use that must comply with the Town of Tyre zoning law.
02 How do I apply for a building permit in Tyre, NY?
To apply for a building permit in Tyre, NY, follow these steps: 1. Contact Zoning Enforcement Officer Reginald Aceto at (315) 835-0163 or zoningofficer@tyreny.gov. 2. Obtain zoning permit application from Zoning Enforcement Officer. 3. Complete application and prepare required site plan and construction documentation. 4. Submit application to Zoning Enforcement Officer with fee. 5. Zoning permits are generally issued within 30 days unless site-plan review, special-use approval, or variance is needed. 6. Confirm with Seneca County Code Enforcement whether a county building permit is also required.
03 How long does it take to get a building permit in Tyre, NY?
Building permit processing times in Tyre, NY typically run Generally 30 days for standard zoning permits; longer if special review required.. Timelines can vary based on project complexity and current department workload.
04 How do I schedule a building inspection in Tyre, NY?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Tyre, NY via: (315) 835-0163, zoningofficer@tyreny.gov. Contact Zoning Enforcement for scheduling requirements..
last verified April 2026 source Town of Tyre Zoning Enforcement Officer ↗ entry id permits/new-york/seneca/tyre