§ 01

Permit authority

Village Code Enforcement Officer

Street address
412 S. Main Street, Northville, NY 12134
Coverage
All properties within the Village of Northville.
Online portal
Code Enforcement
Form-Based
§ 02

When a permit is required

Permit triggers and exempt work for Northville

Building permits are required for most construction work in the Village of Northville.

Note: Confirm exemptions with the Code Enforcement office.

Required documents
  • Building Permit Application
Building code
New York State Uniform Fire Prevention and Building Code
Permit validity
Contact the Code Enforcement Office for permit validity periods.
Contractor requirements
Contractors must comply with New York State licensing and insurance requirements.
§ 03

Application process

Typical processing: Varies; contact the village for expected timelines.

  1. 01
    Download the building permit from the village code-enforcement page.
  2. 02
    Submit to the Village Code Enforcement Officer at 412 S. Main Street, Northville, NY 12134.
  3. 03
    Complete inspections required by the code office.

Typical processing time: Varies; contact the village for expected timelines.

Source: Village Code Enforcement Officer ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • (518) 863-6580 (phone)
  • codes@villageofnorthville.com (email)
§ 05

Frequently asked

Common questions about Northville permits

01 Do I need a building permit in Northville, NY?
Building permits are required for most construction work in the Village of Northville.
02 How do I apply for a building permit in Northville, NY?
To apply for a building permit in Northville, NY, follow these steps: 1. Download the building permit from the village code-enforcement page. 2. Submit to the Village Code Enforcement Officer at 412 S. Main Street, Northville, NY 12134. 3. Complete inspections required by the code office.
03 How long does it take to get a building permit in Northville, NY?
Building permit processing times in Northville, NY typically run Varies; contact the village for expected timelines.. Timelines can vary based on project complexity and current department workload.
04 How do I schedule a building inspection in Northville, NY?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Northville, NY via: (518) 863-6580, codes@villageofnorthville.com.
last verified April 2026 source Village Code Enforcement Officer ↗ entry id permits/new-york/fulton/northville

Educational reference. Permit rules and fees change — confirm current requirements directly with Village Code Enforcement Officer before applying. Jaspector is not legal advice.