§ 01

Permit authority

Village of Magdalena -- Village Hall (Planning, Zoning, and Building Permits)

Street address
108 N. Main Street, Magdalena, NM 87825
Coverage
All construction within the incorporated Village of Magdalena limits. Population approximately 900 to 1,100. Magdalena is located in western Socorro County, approximately 27 miles west of Socorro on U.S. Route 60, near the Plains of San Agustin and the VLA radio telescope site. Very small municipality with limited administrative staff; building department functions may be shared with general village administration or part-time inspector.
Online portal
Village of Magdalena Official Website
In-person only (no dedicated online permit portal)
§ 02

When a permit is required

Permit triggers and exempt work for Magdalena

New construction, additions, alterations, demolition, and installation of mechanical, electrical, and plumbing systems within Magdalena village limits. Contact Village Hall for the specific trigger list applicable to the village.

Note: Thin data. All fee information must be verified directly with the Village of Magdalena at (575) 854-2261. This is a very small community with limited administrative capacity. Fees are likely modest given small project scale and may be in line with NM CID minimums or slightly above.

Required documents
  • Completed application
  • Site plan
  • Contractor license information
  • Property owner information
  • Construction drawings (may be required for larger or more complex projects)
Building code
The Village of Magdalena is expected to be subject to statewide NM building codes (2021 IBC/IRC, 2020 NEC, etc.) as adopted by the state and administered locally. The village may not have formally adopted local amendments beyond the state baseline. Contact Village Hall to confirm the adopted code edition and any local amendments.
Permit validity
Not publicly specified. Standard NM practice (180-day commencement, 180-day continuity) likely applies; confirm with Village Hall.
Owner-builder
NM CID standard rules apply (14.5.2.18 NMAC): one permit per 12 months, primary residence, notarized homeowner application.
Contractor requirements
All contractor work requires a valid NM CID license: GB-2 (residential 1-4 units), GB-98 (commercial). Trade licenses as applicable for electrical, plumbing, and mechanical work.
§ 03

Application process

Typical processing: Not publicly stated. Processing may take 1 to 3 weeks depending on project complexity and staff availability. Contact Village Hall for current timeline.

  1. 01
    Contact Village Hall at (575) 854-2261 to confirm current permit procedures, staffing, and office hours before visiting.
  2. 02
    Obtain the building permit application form from Village Hall. Magdalena may use the NM CID standard building permit application form or a village-specific form.
  3. 03
    For owner-builder projects: obtain notarized CID Homeowner Permit Application (or village equivalent) required.
  4. 04
    Prepare required documents: completed application, site plan, construction drawings or description of work, contractor NM CID license information.
  5. 05
    Submit application and documents to Village Hall.
  6. 06
    Application reviewed by Village building official or administrator. For projects requiring Board of Trustees approval (new commercial, variances, subdivisions), a BOT meeting review may be required.
  7. 07
    Pay applicable permit fees.
  8. 08
    Permit issued; post at job site.
  9. 09
    Schedule inspections by contacting Village Hall. Due to limited local inspector resources, some inspections may be coordinated with NM CID or a contracted inspector.

Typical processing time: Not publicly stated. Processing may take 1 to 3 weeks depending on project complexity and staff availability. Contact Village Hall for current timeline.

Source: Village of Magdalena -- Village Hall (Planning, Zoning, and Building Permits) ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • (575) 854-2261 (phone)
Scheduling deadline
Contact Village Hall for lead time requirements.
Inspection hours
Subject to Village Hall office hours. Contact (575) 854-2261 (may vary; small staff)
Time windows
Subject to Village Hall office hours and inspector availability.

Typical sequence: Standard IBC/IRC sequence (foundation, framing, rough-in, insulation, final) applies. Verify specific Magdalena inspection requirements with Village Hall. Due to very small village size, there may not be a dedicated full-time building inspector. Inspections may be conducted by a part-time village official, a shared-services arrangement, or a contracted private inspector.

§ 05

Frequently asked

Common questions about Magdalena permits

01 Do I need a building permit in Magdalena, NM?
New construction, additions, alterations, demolition, and installation of mechanical, electrical, and plumbing systems within Magdalena village limits. Contact Village Hall for the specific trigger list applicable to the village.
02 How do I apply for a building permit in Magdalena, NM?
To apply for a building permit in Magdalena, NM, follow these steps: 1. Contact Village Hall at (575) 854-2261 to confirm current permit procedures, staffing, and office hours before visiting. 2. Obtain the building permit application form from Village Hall. Magdalena may use the NM CID standard building permit application form or a village-specific form. 3. For owner-builder projects: obtain notarized CID Homeowner Permit Application (or village equivalent) required. 4. Prepare required documents: completed application, site plan, construction drawings or description of work, contractor NM CID license information. 5. Submit application and documents to Village Hall. 6. Application reviewed by Village building official or administrator. For projects requiring Board of Trustees approval (new commercial, variances, subdivisions), a BOT meeting review may be required. 7. Pay applicable permit fees. 8. Permit issued; post at job site. 9. Schedule inspections by contacting Village Hall. Due to limited local inspector resources, some inspections may be coordinated with NM CID or a contracted inspector.
03 How long does it take to get a building permit in Magdalena, NM?
Building permit processing times in Magdalena, NM typically run Not publicly stated. Processing may take 1 to 3 weeks depending on project complexity and staff availability. Contact Village Hall for current timeline.. Timelines can vary based on project complexity and current department workload.
04 How do I schedule a building inspection in Magdalena, NM?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Magdalena, NM via: (575) 854-2261. Contact Village Hall for lead time requirements..
last verified April 2026 source Village of Magdalena -- Village Hall (Planning, Zoning, and Building Permits) ↗ entry id permits/new-mexico/socorro/magdalena

Educational reference. Permit rules and fees change — confirm current requirements directly with Village of Magdalena -- Village Hall (Planning, Zoning, and Building Permits) before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Socorro County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Socorro County jurisdictions →