§ 01

Permit authority

Division of Construction Code Enforcement, Department of Planning and Engineering

Street address
100 Municipal Boulevard, Edison, NJ 08817
Coverage
All properties within Edison Township.
§ 02

When a permit is required

Permit triggers and exempt work for Edison Township

New construction, enlargements, alterations, moves, demolitions, change of use/occupancy, equipment installation.

Repair/replacement of roof covering on detached one or two-family dwellings
Repair/replacement of siding (except polypropylene siding)
Interior/exterior painting, wallpapering, paneling
Replacement of windows or doors (no alteration to original opening framing)
Replacement of trim or moldings
Replacement of kitchen cabinets
Replacement of flooring or carpet
Repair of uncovered porch or stoop
Repairs to existing steps or stairs
Replacement of screens
Replacement of leaders or gutters
Garden sheds 200 sq ft or less, 10 feet or less in height, no utility connections
Fences six feet or less in height (except pool barriers)
Portable/vehicle-mounted generators for carnivals/fairs
Signs 25 sq ft or less, not directly connected to electrical circuit, not more than 6 feet above ground
  • Exempt Repair/replacement of roof covering on detached one or two-family dwellings
  • Exempt Repair/replacement of siding (except polypropylene siding)
  • Exempt Interior/exterior painting, wallpapering, paneling
  • Exempt Replacement of windows or doors (no alteration to original opening framing)
  • Exempt Replacement of trim or moldings
  • Exempt Replacement of kitchen cabinets
  • Exempt Replacement of flooring or carpet
  • Exempt Repair of uncovered porch or stoop
  • Exempt Repairs to existing steps or stairs
  • Exempt Replacement of screens
  • Exempt Replacement of leaders or gutters
  • Exempt Garden sheds 200 sq ft or less, 10 feet or less in height, no utility connections
  • Exempt Fences six feet or less in height (except pool barriers)
  • Exempt Portable/vehicle-mounted generators for carnivals/fairs
  • Exempt Signs 25 sq ft or less, not directly connected to electrical circuit, not more than 6 feet above ground

Note: Exempt from building permit does not mean exempt from zoning requirements. Confirm with Construction Department before proceeding.

Required documents
  • Completed NJ DCA UCC F-100 application
  • Two copies of construction plans by licensed architect/engineer or homeowner for own single-family dwelling
  • Plot plan showing existing and proposed structures, distances to lot lines, and easements
  • Applicable subcode technical sections (F110, F120, F130, F140)
  • Original signatures and seals where necessary
Building code
New Jersey Uniform Construction Code (UCC) based on International Building Code (IBC)
Permit validity
12 months from date of last inspection per NJ UCC.
Owner-builder
Owner-builders permitted for own single-family dwelling; must follow plan requirements.
Contractor requirements
Contractors must hold valid NJ Division of Consumer Affairs license.

Source: Division of Construction Code Enforcement, Department of Planning and Engineering ↗

§ 03

Application process

Typical processing: Minor work (roofing/siding): within 3 days or at counter. Complex projects: varies based on plan review complexity.

  1. 01
    Obtain NJ DCA UCC F-100 Construction Permit Application and applicable subcode technical sections (F110, F120, F130, F140).
  2. 02
    Prepare THREE completed copies with original signatures and original seals where necessary.
  3. 03
    Consult with Engineering Division if Site Improvement Permit is required before building permit.
  4. 04
    Submit application in-person at the Construction Department or by mail.
  5. 05
    City staff reviews completeness and routes to Building, Planning, and Engineering divisions.
  6. 06
    Respond to correction comments and resubmit revised documents if required.
  7. 07
    Pay permit fees and obtain permit before starting work.

Typical processing time: Minor work (roofing/siding): within 3 days or at counter. Complex projects: varies based on plan review complexity.

Source: Division of Construction Code Enforcement, Department of Planning and Engineering ↗

§ 04

Fee schedule

Edison Township building permit fees

Fee type
Amount
01
Plan check fee
Included in permit fee calculation
02
Permit fee formula
Per cubic foot for new construction/additions; per $1,000 of construction value for alterations; state-mandated surcharges apply
03
Reinspection fee
May apply for work not conforming to approved plans
§ 05

Required inspections

Scheduling and sequence

How to schedule
  • 732-248-7257 (phone)
Scheduling deadline
24 hours advance notice required.
Inspection hours
Monday-Friday 9:00 AM to 3:00 PM

Typical sequence: Typical sequence: footing excavation (prior to concrete), foundation wall (prior to backfill), rough plumbing/electrical/fire (prior to insulation), rough framing (prior to insulation with Framing Checklist), insulation (prior to sheetrock), final inspections.

Source: Division of Construction Code Enforcement, Department of Planning and Engineering ↗

§ 06

Frequently asked

Common questions about Edison Township permits

01 Do I need a building permit in Edison Township, NJ?
New construction, enlargements, alterations, moves, demolitions, change of use/occupancy, equipment installation.
02 How much does a building permit cost in Edison Township, NJ?
Building permit fees in Edison Township, NJ are set by the local building department and vary by project type and valuation. Fees are calculated as: Per cubic foot for new construction/additions; per $1,000 of construction value for alterations; state-mandated surcharges apply. Plan check fee: Included in permit fee calculation.
03 How do I apply for a building permit in Edison Township, NJ?
To apply for a building permit in Edison Township, NJ, follow these steps: 1. Obtain NJ DCA UCC F-100 Construction Permit Application and applicable subcode technical sections (F110, F120, F130, F140). 2. Prepare THREE completed copies with original signatures and original seals where necessary. 3. Consult with Engineering Division if Site Improvement Permit is required before building permit. 4. Submit application in-person at the Construction Department or by mail. 5. City staff reviews completeness and routes to Building, Planning, and Engineering divisions. 6. Respond to correction comments and resubmit revised documents if required. 7. Pay permit fees and obtain permit before starting work.
04 How long does it take to get a building permit in Edison Township, NJ?
Building permit processing times in Edison Township, NJ typically run Minor work (roofing/siding): within 3 days or at counter. Complex projects: varies based on plan review complexity.. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Edison Township, NJ?
Not all construction work requires a permit in Edison Township, NJ. The following work is generally exempt: Repair/replacement of roof covering on detached one or two-family dwellings; Repair/replacement of siding (except polypropylene siding); Interior/exterior painting, wallpapering, paneling; Replacement of windows or doors (no alteration to original opening framing); Replacement of trim or moldings; Replacement of kitchen cabinets; Replacement of flooring or carpet; Repair of uncovered porch or stoop; Repairs to existing steps or stairs; Replacement of screens; Replacement of leaders or gutters; Garden sheds 200 sq ft or less, 10 feet or less in height, no utility connections; Fences six feet or less in height (except pool barriers); Portable/vehicle-mounted generators for carnivals/fairs; Signs 25 sq ft or less, not directly connected to electrical circuit, not more than 6 feet above ground. Note: Exempt from building permit does not mean exempt from zoning requirements. Confirm with Construction Department before proceeding. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Edison Township, NJ?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Edison Township, NJ via: 732-248-7257. 24 hours advance notice required..
last verified April 2026 source Division of Construction Code Enforcement, Department of Planning and Engineering ↗ entry id permits/new-jersey/middlesex/edison-township

Educational reference. Permit rules and fees change — confirm current requirements directly with Division of Construction Code Enforcement, Department of Planning and Engineering before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Middlesex County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Middlesex County jurisdictions →