Medford Township, NJ - 2026 Building Permit Guide
How to apply for a building permit in Medford Township, New Jersey. Permit authority, application steps, fees, and inspection requirements.
Permit Authority
All properties within Medford Township, including Pinelands Commission overlay areas.
- Department
- Construction Office / Code Enforcement
- Address
- 17 N. Main Street, Medford, NJ 08055
- Phone
- (609) 654-2608
- Website
- https://medfordtownship.com
Online Permit Portal
Platform: Online forms available; primary submission in-person • Account required: No • Submission: In-person only
Additional resources:
Application Process
- Download or obtain NJ DCA UCC forms from township office or website.
- Complete UCC-F100 Construction Permit Application.
- Complete applicable subcode technical sections.
- Submit two sets of plans drawn in ink or blueprint.
- Include property survey by licensed NJ surveyor.
- Provide contractor licenses and registrations.
- Pay fees at time of application.
- Verify Pinelands Commission approval if property is in Pinelands area.
- Submit documents in-person at Township Office.
- Respond to review comments if required.
- Obtain final permit and post on site before construction begins.
Typical processing time: 20 working days for complete applications (unless extended by written agreement).
General Requirements
A construction permit is required for most work as per NJ Uniform Construction Code (UCC).
Required Documents
- UCC-F100 Construction Permit Application
- Building Subcode Technical Section (F110)
- Electrical Subcode Technical Section (F120)
- Plumbing Subcode Technical Section (F130)
- Fire Protection Subcode Technical Section (F140)
- Mechanical Subcode Technical Section (F145) if applicable
- Two sets of construction plans
- Property survey showing lot lines and dimensions
- Proof of contractor insurance and NJ registration
- Home Improvement Contractor registration (residential)
- Permit validity
- 12 months from the date of the most recent inspection per N.J.A.C. 5:23-2.18.
- Building code
- NJ Uniform Construction Code (UCC)
- Owner-builder
- Owner-builders must comply with NJ UCC requirements and contractor licensing where applicable.
- Contractor requirements
- Contractors must hold valid NJ licenses, insurance, and be registered as Home Improvement Contractors for residential work.
Fees
- Minimum permit fee
- Varies by subcode
- Permit fee formula
- New Construction: Based on building volume per NJAC 5:23-2.28; Renovations: Based on estimated cost of work.
- Payment note
- Proposed utility extensions require Township Engineer review ($500 fee when applicable). Fees paid before permit issuance.
Fees change. Verify current amounts at the official fee schedule.
Work That Does NOT Require a Permit
- Ordinary maintenance work
- Minor work as classified by NJ UCC
- Emergency work (permit required within 72 hours)
Important: Pinelands Commission approval required for properties within Pinelands area. All local taxes and assessments must be paid before permit issuance. Confirm edge cases with Code Enforcement before proceeding.
Inspections
How to Schedule
- inspections@medfordtownship.com (email)
- Construction Office (in-person)
- Scheduling deadline
- Written request required, submitted at least 24 hours in advance.
- Inspection hours
- Building and Plumbing: Monday-Friday, 8:30 AM to 2:00 PM; Electrical and Mechanical: Monday-Friday, 8:30 AM to 2:00 PM; Fire Protection: Tuesday and Thursday, 8:30 AM to 12:00 Noon
Typical inspection sequence: Required inspections: Footings (before concrete), Foundation/walls to grade (before backfill), Utility services (including septic), Structural framing/connections/sheathing/insulation, Electrical rough wiring/panel/service, Rough plumbing, HVAC duct systems, Framing inspection, Insulation inspection, Final inspections (all subcodes).
All township inspectors carry photo identification. Minor work classification requires only final inspections.
Additional Resources
- Building code: NJ Uniform Construction Code (UCC)
- Verify contractor license: NJ Division of Consumer Affairs
- Zoning information: View zoning info
- NJ DCA Forms
- Framing Checklist (UCC-F390)
- Pinelands Commission
- Burlington County Health Department (Well/Septic)
- Call Before You Dig (811)
- License lookup guide: New Jersey Contractor License Requirements
- Contract template: New Jersey Homeowner-Contractor Agreement
- New Jersey hub: New Jersey Contractor License & Permit Hub
Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Construction Office / Code Enforcement before applying.
Frequently Asked Questions
Medford Township Building Permit FAQ
- Do I need a building permit in Medford Township, NJ?
- A construction permit is required for most work as per NJ Uniform Construction Code (UCC).
- How much does a building permit cost in Medford Township, NJ?
- The minimum permit fee is Varies by subcode. Fees are calculated as: New Construction: Based on building volume per NJAC 5:23-2.28; Renovations: Based on estimated cost of work..
- How do I apply for a building permit in Medford Township, NJ?
- 1. Download or obtain NJ DCA UCC forms from township office or website. 2. Complete UCC-F100 Construction Permit Application. 3. Complete applicable subcode technical sections. 4. Submit two sets of plans drawn in ink or blueprint. 5. Include property survey by licensed NJ surveyor. 6. Provide contractor licenses and registrations. 7. Pay fees at time of application. 8. Verify Pinelands Commission approval if property is in Pinelands area. 9. Submit documents in-person at Township Office. 10. Respond to review comments if required. 11. Obtain final permit and post on site before construction begins.
- How long does it take to get a building permit in Medford Township, NJ?
- Typical processing time is 20 working days for complete applications (unless extended by written agreement)..
- What work is exempt from building permits in Medford Township, NJ?
- The following work is generally exempt: Ordinary maintenance work; Minor work as classified by NJ UCC; Emergency work (permit required within 72 hours). Note: Pinelands Commission approval required for properties within Pinelands area. All local taxes and assessments must be paid before permit issuance. Confirm edge cases with Code Enforcement before proceeding.
- How do I schedule a building inspection in Medford Township, NJ?
- Inspections can be scheduled via: inspections@medfordtownship.com, Construction Office. Written request required, submitted at least 24 hours in advance..
Need help with your project?
Navigating permits in Medford Township can be complicated.
Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.
Learn how Jaspector worksOther cities in Burlington County
View all Burlington County jurisdictions →