City Building Permits

Town of Nottingham, NH - 2026 Building Permit Guide

How to apply for a building permit in Town of Nottingham, New Hampshire. Permit authority, application steps, fees, and inspection requirements.

New Hampshire Rockingham County Updated March 2026

Permit Authority

Town of Nottingham issues building permits within town limits.

Department
Building/Code/Health Inspector
Address
139 Stage Road / P.O. Box 114, Nottingham, NH 03290
Phone
(603) 679-9597

Online Permit Portal

Platform: Town website; downloadable forms • Account required: No • Submission: In-person only

Application Process

Typical processing time: 24-48 hours for complete applications; 30-day maximum

Source: Building/Code/Health Inspector

General Requirements

All new construction including porches, swimming pools (above and

Required Documents

  • Construction plans to scale
  • site plan with setbacks from property lines
Building code
NH State Building Code (RSA 155-A)
Owner-builder
Not specified publicly
Contractor requirements
State-licensed trades required; inspections required for

Fees

Minimum permit fee
No charge for sheds under 145 sq ft
Plan check fee
Not specified separately
Permit fee formula
Not specified publicly; see fee schedule on department page
Payment note
All fees must be paid before permit review begins

Fees change. Verify current amounts at the official fee schedule.

Work That Does NOT Require a Permit

  • Sheds under 145 square feet (permit required but no fee charged)

Inspections

How to Schedule

Typical inspection sequence: Contact department; required inspections list available at

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Building/Code/Health Inspector before applying.

Frequently Asked Questions

Town of Nottingham Building Permit FAQ

Do I need a building permit in Town of Nottingham, NH?
All new construction including porches, swimming pools (above and
How much does a building permit cost in Town of Nottingham, NH?
The minimum permit fee is No charge for sheds under 145 sq ft. Fees are calculated as: Not specified publicly; see fee schedule on department page. Plan check fee: Not specified separately.
How long does it take to get a building permit in Town of Nottingham, NH?
Typical processing time is 24-48 hours for complete applications; 30-day maximum.
What work is exempt from building permits in Town of Nottingham, NH?
The following work is generally exempt: Sheds under 145 square feet (permit required but no fee charged).
How do I schedule a building inspection in Town of Nottingham, NH?
Inspections can be scheduled via: Town website; downloadable forms.

Need help with your project?

Navigating permits in Town of Nottingham can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.