When a permit is required
Permit triggers and exempt work for Sherman County
Building permits required for all non-farm structures in zoned areas before construction begins under Neb. Rev. Stat. § 23-114.04
- Exempt Buildings on farmsteads of 20+ acres producing $1,000+ annually in farm products (Neb. Rev. Stat. § 23-114.03)
Note: Agricultural exemption applies only to farmsteads meeting acreage and production requirements
- Written application
- Site plans showing building location, dimensions, and use
- Estimated project cost
- Proof of zoning compliance
- Sanitation, plumbing, and sewage disposal compliance documentation
- Building code
- If not locally adopted, 2018 Uniform Plumbing Code applies statewide
Application process
Application → plan check → issuance → inspection → final
- 01 Submit written application to Sherman County Planning & Zoning Administrator
- 02 Include site plans showing building location, dimensions, use, and estimated cost
- 03 Ensure plans conform to all zoning regulations
- 04 Payment of applicable permit fee upon issuance
Required inspections
Scheduling and sequence
- Contact county building inspector directly (phone)
Typical sequence: Foundation and footings (before backfilling), plumbing rough-in, framing and rough electrical/mechanical, final inspection upon completion
Frequently asked
Common questions about unincorporated Sherman County permits
01 Do I need a building permit in unincorporated Sherman County, NE? ▸
02 How do I apply for a building permit in unincorporated Sherman County, NE? ▸
03 What work is exempt from building permits in unincorporated Sherman County, NE? ▸
04 How do I schedule a building inspection in unincorporated Sherman County, NE? ▸