When a permit is required
Permit triggers and exempt work for Plains
New construction, additions, alterations, renovations, repairs, demolition, and structural modifications
- Exempt Farm and ranch buildings
- Exempt Mining buildings on mining property
- Exempt Petroleum refineries and pulp and paper mills (except office/shop buildings)
- Exempt Residential buildings under five dwelling units (except transient use)
- Exempt Private garages and storage buildings for owner's personal use
- Exempt Agricultural structures per state exemptions
Note: Trade permits required where applicable (electrical, plumbing, mechanical). Per Montana state law applicable in town
- Completed application
- Construction plans and specifications
- Architectural drawings
- Site plans
- Proof of ownership
- Town-specific forms
- Building code
- 2021 International Building Code (IBC 2021) as adopted by the State of Montana and incorporated into Plains municipal code
Application process
Typical processing: Approximately 3 weeks (standard Montana state review timeframe; local may vary)
- 01 Contact Town of Plains Town Hall to determine local vs. state jurisdiction
- 02 Prepare required construction documents: plans, drawings, site plans, specifications
- 03 Submit Building Permit Application and construction documents to Town Hall
- 04 Town reviews for compliance with Plains ordinances and adopted building standards
- 05 Upon approval, obtain permit and pay associated fees
- 06 Proceed with construction per approved plans
- 07 Schedule required inspections with town
- 08 After passing all required inspections, obtain certificate of occupancy
Typical processing time: Approximately 3 weeks (standard Montana state review timeframe; local may vary)
Required inspections
Scheduling and sequence
- Contact (406) 826-3411 to schedule inspections (phone)
- Inspection hours
- Monday-Friday 9:00 a.m. to 5:00 p.m.
Typical sequence: Typical inspection sequence: foundation, framing, electrical, plumbing, mechanical, and final. Town Hall coordinates scheduling. Final inspection approval required before certificate of occupancy
Frequently asked
Common questions about Plains permits
01 Do I need a building permit in Plains, MT? ▸
02 How do I apply for a building permit in Plains, MT? ▸
03 How long does it take to get a building permit in Plains, MT? ▸
04 What work is exempt from building permits in Plains, MT? ▸
05 How do I schedule a building inspection in Plains, MT? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Town of Plains Building/Permitting Department before applying. Jaspector is not legal advice.