§ 01

Permit authority

Town of Sheridan; Montana Building Codes Program (state permits)

Street address
Town Hall, Sheridan, MT (specific street address not publicly listed); State: P.O. Box 200517, Helena, MT 59602
Coverage
Town of Sheridan administers local zoning and site plan review. Most building permits are issued by the Montana Building Codes Program at the state level unless Sheridan has adopted local building code enforcement
Online portal
Town of Sheridan Town Hall
Paper or online submission (varies by jurisdiction)
§ 02

When a permit is required

Permit triggers and exempt work for Sheridan

Building permits required for all new construction and additions before work begins

Private storage buildings and sheds (200 sq ft max, 12 ft max height)
Farm/ranch buildings
Minor repairs and maintenance
  • Exempt Private storage buildings and sheds (200 sq ft max, 12 ft max height)
  • Exempt Farm/ranch buildings
  • Exempt Minor repairs and maintenance

Note: Standard Montana exemptions likely apply. Contact Town Hall to confirm local exemptions before starting work

Required documents
  • Building Permit Application
  • Construction plans and specifications
  • Site plan
  • Proof of zoning compliance
  • Building cost estimate
Building code
Montana Building Codes (state-adopted); town may have local zoning requirements

Source: Town of Sheridan; Montana Building Codes Program (state permits) ↗

§ 03

Application process

Typical processing: Local: varies with Council meeting schedule; State: 2-3 weeks for plan review

  1. 01
    Contact Town of Sheridan Town Hall (406-842-5431) to verify if local or state permits required
  2. 02
    For local permits: verify zoning compliance, prepare site plan per town requirements, submit application to Town Hall
  3. 03
    Town Council reviews at regular meetings (2nd Monday, 6 pm)
  4. 04
    For state building permits: prepare construction plans and Building Permit/Plan Review Application
  5. 05
    Submit to Montana Building Codes Program
  6. 06
    State conducts plan review (2-3 weeks if plans complete)
  7. 07
    Upon approval, obtain permit and begin construction

Typical processing time: Local: varies with Council meeting schedule; State: 2-3 weeks for plan review

Source: Town of Sheridan; Montana Building Codes Program (state permits) ↗

§ 04

Fee schedule

Sheridan building permit fees

Fee type
Amount
01
Permit fee formula
Calculated as percentage of building valuation by Building Codes Program (typically 1-2% of building valuation)
§ 05

Required inspections

Scheduling and sequence

How to schedule
  • Contact appropriate authority (Town or State) to schedule inspections (phone)

Typical sequence: Plan review; foundation; framing; systems (electrical, plumbing, mechanical); final. Specific inspection sequence varies based on project type and jurisdiction

Source: Town of Sheridan; Montana Building Codes Program (state permits) ↗

§ 06

Frequently asked

Common questions about Sheridan permits

01 Do I need a building permit in Sheridan, MT?
Building permits required for all new construction and additions before work begins
02 How much does a building permit cost in Sheridan, MT?
Building permit fees in Sheridan, MT are set by the local building department and vary by project type and valuation. Fees are calculated as: Calculated as percentage of building valuation by Building Codes Program (typically 1-2% of building valuation).
03 How do I apply for a building permit in Sheridan, MT?
To apply for a building permit in Sheridan, MT, follow these steps: 1. Contact Town of Sheridan Town Hall (406-842-5431) to verify if local or state permits required 2. For local permits: verify zoning compliance, prepare site plan per town requirements, submit application to Town Hall 3. Town Council reviews at regular meetings (2nd Monday, 6 pm) 4. For state building permits: prepare construction plans and Building Permit/Plan Review Application 5. Submit to Montana Building Codes Program 6. State conducts plan review (2-3 weeks if plans complete) 7. Upon approval, obtain permit and begin construction
04 How long does it take to get a building permit in Sheridan, MT?
Building permit processing times in Sheridan, MT typically run Local: varies with Council meeting schedule; State: 2-3 weeks for plan review. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Sheridan, MT?
Not all construction work requires a permit in Sheridan, MT. The following work is generally exempt: Private storage buildings and sheds (200 sq ft max, 12 ft max height); Farm/ranch buildings; Minor repairs and maintenance. Note: Standard Montana exemptions likely apply. Contact Town Hall to confirm local exemptions before starting work When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Sheridan, MT?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Sheridan, MT via: Contact appropriate authority (Town or State) to schedule inspections.
last verified March 2026 source Town of Sheridan; Montana Building Codes Program (state permits) ↗ entry id permits/montana/madison/sheridan

Educational reference. Permit rules and fees change — confirm current requirements directly with Town of Sheridan; Montana Building Codes Program (state permits) before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Madison County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Madison County jurisdictions →