jaspector
City building permits

Town of Grass Range

How to apply for a building permit in Town of Grass Range, Montana. Permit authority, application steps, fees, and inspection requirements.

Last verified
March 2026
On this page 6
§ 01

Permit authority

Fergus County Planning Office (Local Authority) / Montana Building Codes Program (State Authority)

Street address
602 Main Street, Grass Range, MT 59032
Coverage
Incorporated Town of Grass Range; building permits issued through Fergus County Planning Office.
Online portal
Montana EBIZ Portal
Montana Building Codes Program Online Portal
§ 02

When a permit is required

Permit triggers and exempt work for Grass Range

Follows Montana state standards (confirm locally): new construction, additions, significant modifications, structural work

Farm/ranch buildings
Small residential buildings (under 5 units)
Private garages
Certain repairs
  • Exempt Farm/ranch buildings
  • Exempt Small residential buildings (under 5 units)
  • Exempt Private garages
  • Exempt Certain repairs

Note: Confirm with Planning Office or town before proceeding.

Required documents
  • Building Permit Application (local or state form)
  • Site plan showing property boundaries and building location
  • Architectural/structural plans
  • Mechanical/electrical/plumbing plans (if applicable)
  • Project cost estimate
Building code
Likely 2021 International Building Codes (state standard); confirm locally
Permit validity
Likely 180 days (standard Montana)
Owner-builder
Owner may act as contractor (standard Montana practice)
Contractor requirements
Montana state contractor registration/ICEC required; local town/county business license may be needed
§ 03

Application process

Typical processing: Typically 2-3 weeks for plan review (standard Montana)

  1. 01
    Contact Fergus County Planning Office at (406) 535-9046 or town hall at (406) 428-2174
  2. 02
    Determine if permit issued locally or through state
  3. 03
    Obtain applicable application forms
  4. 04
    Prepare construction plans
  5. 05
    Submit application with fees
  6. 06
    Receive approval or comments
  7. 07
    Address comments if needed
  8. 08
    Pay final fees and receive permit
  9. 09
    Schedule inspections

Typical processing time: Typically 2-3 weeks for plan review (standard Montana)

Source: Fergus County Planning Office (Local Authority) / Montana Building Codes Program (State Authority) ↗

§ 04

Fee schedule

Grass Range building permit fees

Fee type
Amount
01
Permit fee formula
Likely 1-2% of building valuation (standard Montana). Contact Fergus County Planning Office at (406) 535-9046 for current rates and fee schedule.
§ 05

Required inspections

Scheduling and sequence

How to schedule
  • (406) 535-9046 (county) or (406) 428-2174 (town) (phone)
Scheduling deadline
Typically within 24-72 hours

Typical sequence: Multiple inspections required by phase. Written inspection reports provided. Corrections made before proceeding. Final inspection grants Certificate of Occupancy.

Source: Fergus County Planning Office (Local Authority) / Montana Building Codes Program (State Authority) ↗

§ 06

Frequently asked

Common questions about Grass Range permits

01 Do I need a building permit in Grass Range, MT?
Follows Montana state standards (confirm locally): new construction, additions, significant modifications, structural work
02 How much does a building permit cost in Grass Range, MT?
Building permit fees in Grass Range, MT are set by the local building department and vary by project type and valuation. Fees are calculated as: Likely 1-2% of building valuation (standard Montana). Contact Fergus County Planning Office at (406) 535-9046 for current rates and fee schedule..
03 How do I apply for a building permit in Grass Range, MT?
To apply for a building permit in Grass Range, MT, follow these steps: 1. Contact Fergus County Planning Office at (406) 535-9046 or town hall at (406) 428-2174 2. Determine if permit issued locally or through state 3. Obtain applicable application forms 4. Prepare construction plans 5. Submit application with fees 6. Receive approval or comments 7. Address comments if needed 8. Pay final fees and receive permit 9. Schedule inspections
04 How long does it take to get a building permit in Grass Range, MT?
Building permit processing times in Grass Range, MT typically run Typically 2-3 weeks for plan review (standard Montana). Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Grass Range, MT?
Not all construction work requires a permit in Grass Range, MT. The following work is generally exempt: Farm/ranch buildings; Small residential buildings (under 5 units); Private garages; Certain repairs. Note: Confirm with Planning Office or town before proceeding. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Grass Range, MT?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Grass Range, MT via: (406) 535-9046 (county) or (406) 428-2174 (town). Typically within 24-72 hours.

Educational reference. Permit rules and fees change — confirm current requirements directly with Fergus County Planning Office (Local Authority) / Montana Building Codes Program (State Authority) before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Fergus County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Fergus County jurisdictions →