jaspector
City building permits

Cameron

How to apply for a building permit in Cameron, Missouri. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

Building Permits & Inspections, City of Cameron

Street address
205 N. Main St., Cameron, MO 64429 (mailing address P.O. Box 20, Cameron, MO 64429-0020)
Coverage
The department enforces the 2015 ICC Building Codes, the 2015 IRC (with minor revisions since May 2017), and the 2017 NEC for all new construction and improvements within city limits. citeturn7view0turn10view0
§ 02

When a permit is required

Permit triggers and exempt work for Cameron

Cameron requires permits for all new buildings, additions, remodels, accessory structures, and demolition. citeturn7view0

The public materials do not list exempt work; verify with the department. (thin public information)
  • Exempt The public materials do not list exempt work; verify with the department. (thin public information)
Required documents
  • When a permit is required: Cameron requires permits for all new buildings, additions, remodels, accessory structures, and demolition. citeturn7view0
  • Required documents: Submit two sets of stamped plans, a surveyor’s site plan showing setbacks/flood data, and details covering bracing, plumbing, electrical, and mechanical systems. citeturn10view0
  • Permit validity/expiration: Permits expire if construction does not begin within 180 days. citeturn10view0
  • Owner-builder rules if available: Occupational licenses are required for every worker, and registered trades must present proof of Master licensure. citeturn10view0
  • Contractor license requirements: Electrical, mechanical, and plumbing contractors must hold a Master license from a nationally accredited testing company. citeturn10view0
  • Building code adopted: The city enforces the 2015 International Building Codes (including the 2015 IRC with minor revisions) and the 2017 NEC. citeturn7view0turn10view0
Building code
The city enforces the 2015 International Building Codes (including the 2015 IRC with minor revisions) and the 2017 NEC. citeturn7view0turn10view0
Permit validity
Permits expire if construction does not begin within 180 days. citeturn10view0
Owner-builder
Occupational licenses are required for every worker, and registered trades must present proof of Master licensure. citeturn10view0
Contractor requirements
Electrical, mechanical, and plumbing contractors must hold a Master license from a nationally accredited testing company. citeturn10view0
§ 03

Application process

Typical processing: Plan review is targeted at 30 working days; no other timeframe is public. citeturn10view0

  1. 01
    Submit two sets of drawings (foundation plan, floor plans, elevations, wall sections, emergency egress, wall bracing, and engineer/architect stamp) plus a detailed site plan before the inspector reviews the project. citeturn10view0
  2. 02
    Plan review should not take more than 30 working days, and construction must start within 180 days of issuance. citeturn10view0
  3. 03
    Pay permit fees based on finished square footage or estimated cost along with any stormwater, water tap, or sewer impact fees before the permit is issued. citeturn9view0turn10view0
  4. 04
    Acquire occupational licenses for everyone working on the project, and ensure electrical/mechanical/plumbing contractors show their Master licenses even if the general contractor has a blanket license. citeturn10view0
  5. 05
    Schedule inspections by calling (816) 632-2177 or emailing pbeckwith@cameronmo.com with 24 hours’ notice (4 hours for concrete/sewer); silt fences must stay in place and access must be maintained. citeturn10view0
  6. 06
    Request the occupancy inspection once all rough-ins, driveways, and site work comply; the inspector may issue a temporary occupancy while landscaping wraps up. citeturn10view0

Typical processing time: Plan review is targeted at 30 working days; no other timeframe is public. citeturn10view0

§ 04

Fee schedule

Cameron building permit fees

Fee type
Amount
01
Minimum permit fee
$40 for non-electrical remodeling and $60 for electrical minimums. citeturn9view0
02
Plan check fee
Stormwater plan review is $200 for single-family and $450 plus $50 per acre for larger sites; no separate building plan check fees are listed. citeturn9view0
03
Permit fee formula
New construction is $0.67 per square foot, remodels are $0.33 per square foot, and miscellaneous work uses estimated cost brackets (0.01 × estimated cost for projects ≥ $6,001); utility tap, stormwater review, and street-cut fees are also listed. citeturn9view0
04
Reinspection fee
A $50 late fee applies if construction begins before the permit is purchased, and demolition, reinspection, and extension fees are enumerated in the schedule. citeturn9view0

The building page links to the city’s Online Bill Pay portal for fee settlement. citeturn7view0

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • Call (816) 632-2177 or email pbeckwith@cameronmo.com for inspections with 24 hours’ notice (4 hours for concrete/sewer work). citeturn10view0 ()
Inspection hours
The Building Department is open Monday–Friday, 8:00 a.m.–5:00 p.m. citeturn7view0

Typical sequence: The Building Guidelines list footing, wall, sewer, ground rough, erosion, wall bracing, rough-in, driveway/sidewalk, and occupancy inspections. citeturn10view0

§ 06

Frequently asked

Common questions about Cameron permits

01 Do I need a building permit in Cameron, MO?
Cameron requires permits for all new buildings, additions, remodels, accessory structures, and demolition. citeturn7view0
02 How much does a building permit cost in Cameron, MO?
Building permit fees in Cameron, MO are set by the local building department and vary by project type and valuation. The minimum permit fee is $40 for non-electrical remodeling and $60 for electrical minimums. citeturn9view0. Fees are calculated as: New construction is $0.67 per square foot, remodels are $0.33 per square foot, and miscellaneous work uses estimated cost brackets (0.01 × estimated cost for projects ≥ $6,001); utility tap, stormwater review, and street-cut fees are also listed. citeturn9view0. Plan check fee: Stormwater plan review is $200 for single-family and $450 plus $50 per acre for larger sites; no separate building plan check fees are listed. citeturn9view0.
03 How do I apply for a building permit in Cameron, MO?
To apply for a building permit in Cameron, MO, follow these steps: 1. Submit two sets of drawings (foundation plan, floor plans, elevations, wall sections, emergency egress, wall bracing, and engineer/architect stamp) plus a detailed site plan before the inspector reviews the project. citeturn10view0 2. Plan review should not take more than 30 working days, and construction must start within 180 days of issuance. citeturn10view0 3. Pay permit fees based on finished square footage or estimated cost along with any stormwater, water tap, or sewer impact fees before the permit is issued. citeturn9view0turn10view0 4. Acquire occupational licenses for everyone working on the project, and ensure electrical/mechanical/plumbing contractors show their Master licenses even if the general contractor has a blanket license. citeturn10view0 5. Schedule inspections by calling (816) 632-2177 or emailing pbeckwith@cameronmo.com with 24 hours’ notice (4 hours for concrete/sewer); silt fences must stay in place and access must be maintained. citeturn10view0 6. Request the occupancy inspection once all rough-ins, driveways, and site work comply; the inspector may issue a temporary occupancy while landscaping wraps up. citeturn10view0
04 How long does it take to get a building permit in Cameron, MO?
Building permit processing times in Cameron, MO typically run Plan review is targeted at 30 working days; no other timeframe is public. citeturn10view0. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Cameron, MO?
Not all construction work requires a permit in Cameron, MO. The following work is generally exempt: The public materials do not list exempt work; verify with the department. (thin public information). When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Cameron, MO?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Cameron, MO via: Call (816) 632-2177 or email pbeckwith@cameronmo.com for inspections with 24 hours’ notice (4 hours for concrete/sewer work). citeturn10view0.
last verified April 2026 entry id permits/missouri/clinton/cameron

Educational reference. Permit rules and fees change — confirm current requirements directly with Building Permits & Inspections, City of Cameron before applying. Jaspector is not legal advice.