§ 01

Permit authority

Tippah County Board of Supervisors

Street address
101 East Spring Street, 2nd Floor, Ripley, MS 38663
Coverage
Unincorporated areas of Tippah County, Mississippi. County has no county-wide zoning ordinance for unincorporated areas.
§ 02

When a permit is required

Permit triggers and exempt work for Tippah County

Permit triggers per Mississippi Code § 17-2 baseline: new residential and commercial construction, substantial renovation or enlargement, septic/onsite wastewater system installation (MSDH permit required separately), and any development within a FEMA Special Flood Hazard Area.

Farm structures exempt from state building code provisions under Mississippi Code § 17-2-7, except for structures in designated flood hazard areas (NFIP requirement applies)
  • Exempt Farm structures exempt from state building code provisions under Mississippi Code § 17-2-7, except for structures in designated flood hazard areas (NFIP requirement applies)

Note: Agricultural exemptions do not apply to structures in FEMA Special Flood Hazard Areas (NFIP requirement applies). Unincorporated Tippah County has no county-wide zoning, so zoning restrictions do not apply outside designated flood areas.

Required documents
  • Completed permit application
  • Site plan
  • Property description
  • Project scope information
Building code
Tippah County has not adopted a comprehensive county-wide building code ordinance for unincorporated areas. Mississippi Code § 17-2-5 permits but does not mandate that county boards of supervisors adopt minimum building codes. Confirm directly with Board of Supervisors at (662) 837-3655 whether any code edition has been adopted.
Permit validity
Not specified; contact Board of Supervisors for validity period
Contractor requirements
Not specified; contact Board of Supervisors
§ 03

Application process

Typical processing: Not specified; contact Board of Supervisors for timeline

  1. 01
    Confirm the property is in unincorporated Tippah County (not within a city or town's limits) by contacting the Tax Assessor/Collector or Chancery Clerk
  2. 02
    Contact the Tippah County Board of Supervisors office at (662) 837-3655 for permit application forms applicable to your project type
  3. 03
    Submit application with site plan, property description, and project scope to the Board of Supervisors office or Chancery Clerk
  4. 04
    Pay applicable permit fees upon approval
  5. 05
    Obtain permit before commencing construction
  6. 06
    Schedule any required inspections through the county

Typical processing time: Not specified; contact Board of Supervisors for timeline

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • (662) 837-3655 (phone)

Typical sequence: Inspection requirements for unincorporated Tippah County not specified in publicly available sources. Contact Board of Supervisors at (662) 837-3655 to confirm whether county-level building inspections are conducted and required inspection stages.

§ 05

Frequently asked

Common questions about unincorporated Tippah County permits

01 Do I need a building permit in unincorporated Tippah County, MS?
Permit triggers per Mississippi Code § 17-2 baseline: new residential and commercial construction, substantial renovation or enlargement, septic/onsite wastewater system installation (MSDH permit required separately), and any development within a FEMA Special Flood Hazard Area.
02 How do I apply for a building permit in unincorporated Tippah County, MS?
To apply for a building permit in unincorporated Tippah County, MS, follow these steps: 1. Confirm the property is in unincorporated Tippah County (not within a city or town's limits) by contacting the Tax Assessor/Collector or Chancery Clerk 2. Contact the Tippah County Board of Supervisors office at (662) 837-3655 for permit application forms applicable to your project type 3. Submit application with site plan, property description, and project scope to the Board of Supervisors office or Chancery Clerk 4. Pay applicable permit fees upon approval 5. Obtain permit before commencing construction 6. Schedule any required inspections through the county
03 How long does it take to get a building permit in unincorporated Tippah County, MS?
Building permit processing times in unincorporated Tippah County, MS typically run Not specified; contact Board of Supervisors for timeline. Timelines can vary based on project complexity and current department workload.
04 What work is exempt from building permits in unincorporated Tippah County, MS?
Not all construction work requires a permit in unincorporated Tippah County, MS. The following work is generally exempt: Farm structures exempt from state building code provisions under Mississippi Code § 17-2-7, except for structures in designated flood hazard areas (NFIP requirement applies). Note: Agricultural exemptions do not apply to structures in FEMA Special Flood Hazard Areas (NFIP requirement applies). Unincorporated Tippah County has no county-wide zoning, so zoning restrictions do not apply outside designated flood areas. When in doubt, confirm with the local building department before starting work.
05 How do I schedule a building inspection in unincorporated Tippah County, MS?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in unincorporated Tippah County, MS via: (662) 837-3655.
last verified April 2026 entry id permits/mississippi/tippah/unincorporated

Educational reference. Permit rules and fees change — confirm current requirements directly with Tippah County Board of Supervisors before applying. Jaspector is not legal advice.