When a permit is required
Permit triggers and exempt work for Red Banks
A building permit is required for new construction, building additions or enlargements, change of use or occupancy, major renovations, demolition, all storage buildings/sheds (regardless of size if permanent foundation), mobile home installation, and any work requiring code compliance verification.
- Completed permit application
- Site plans
- Construction documents
- Property legal description
- Contractor license numbers (electrical, mechanical, plumbing)
- Building code
- 2018 International Building Code (IBC), 2018 International Residential Code (IRC), 2020 National Electrical Code (NEC), 2018 International Mechanical Code (IMC), 2018 International Plumbing Code (IPC)
- Permit validity
- A building permit is valid for six (6) months. If any inspection is made within the initial six-month period, the permit is automatically extended for an additional six months from the date of that inspection.
- Owner-builder
- Owner-occupants may obtain a building permit for their own primary residence but must still hire licensed contractors for all electrical, plumbing, and mechanical work.
- Contractor requirements
- Electrical, mechanical, and plumbing contractors must be licensed with the Mississippi State Board of Contractors (MSBOC) and must have their license number available at the time of the permitting appointment.
Application process
Typical processing: Variable; appointments and plan review scheduling required
- 01 Determine the zoning use of the property by contacting the Zoning office at (662) 252-3663 with property owner name or parcel number.
- 02 Schedule an appointment prior to plan review by calling (662) 252-3663. Appointments are required before plan review.
- 03 Submit the completed permit application through the online GeoPermits portal or in person at 545 JM Ash Drive, Holly Springs, MS 38635.
- 04 Provide required documentation: site plans, construction documents, property legal description, and contractor license numbers for electrical, mechanical, and plumbing work.
- 05 Submit payment in full before scheduling inspections. Payment is required prior to inspection scheduling.
- 06 Receive permit and begin construction in compliance with adopted codes.
- 07 Schedule required inspections through the online portal or by calling (662) 252-3663 with at least 24-hour notice.
Typical processing time: Variable; appointments and plan review scheduling required
Source: Marshall County Department of Planning, Zoning and Development ↗
Fee schedule
Red Banks building permit fees
Payment accepted as cash, check, or money order. Payment must be submitted in full before inspections are scheduled. Contact (662) 252-3663 for complete and current fee schedule.
Required inspections
Scheduling and sequence
- GeoPermits portal (online)
- (662) 252-3663 (phone)
- Scheduling deadline
- Pre-scheduled inspections via online portal take precedence over last-minute call-in requests
- Inspection hours
- Monday–Friday, 8:00 AM–5:00 PM
Typical sequence: Required inspection stages for new residential construction: Footer/Slab Plumbing Inspection, Foundation Inspection, Framing/Plumbing/Mechanical Rough-In, Insulation Inspection, Electrical Final, Final Inspection.
Source: Marshall County Department of Planning, Zoning and Development ↗
Frequently asked
Common questions about Red Banks permits
01 Do I need a building permit in Red Banks, MS? ▸
02 How much does a building permit cost in Red Banks, MS? ▸
03 How do I apply for a building permit in Red Banks, MS? ▸
04 How long does it take to get a building permit in Red Banks, MS? ▸
05 How do I schedule a building inspection in Red Banks, MS? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Marshall County Department of Planning, Zoning and Development before applying. Jaspector is not legal advice.